LIKE HEADERS, OUTSIDE corners and channels can be built in a number of different ways, and pref­erences tend to be regional. The most common con­structions are shown in the illustration below. A two-stud outside corner works well in most cases, but if you are planning to install clapboard or fiber-cement siding directly to the studs (with no exterior sheathing), you’ll need more backing at the outside corners. A blocked-up corner provides more backing and makes good use of 2x offcuts.

In addition, all of these outside corner configura­tions provide backing on the inside of the wall for drywall or other wallboard.

Channels (sometimes called tees) are most easily made w;th a flat stud or blocks nailed between two regular studs. I place a crowned or knot-filled stud between two good studs. In some parts of the coun­try, framers build ladder-type channels to provide backing at intersecting walls. Building ladder back­ing doesn’t save a lot on materials, but it does allow more insulation to be inserted at those spots.

Both corners and channels are nailed together with one 16d nail every 2 ft. o. c. When nailing channels to the top and bottom plates, make sure that the flat stud is oriented correctly to provide backing for an intersecting wall. It’s not difficult to put in a channel upside-down.

BUILDING OUTSIDE CORNERS AND CHANNELS

 

Intersecting wall

 

Iwo*stud corner

 

Blocked-up corner

 

Ladder-backing channel

 

Three-stud channel

 

An outside corner can be made with two studs and three short blocks.

 

A channel can be made from three studs or from two studs and three short, flat blocks nailed between them.

 

A channel made with short 2x$ nailed between the studs allows the area to be well insulated.

 

Techniaues BUILDING CORNERS AND CHANNELS

Шcorner saves a 2x stud fallows for more insulation «the wall.

Techniaues BUILDING CORNERS AND CHANNELS

Techniaues BUILDING CORNERS AND CHANNELS

MAKE A CHANNEL.

A pneumatic nailer makes quick work of this assembly, which consists of two studs separated by 2×4 blocking.

Подпись: 'XV ГTechniaues BUILDING CORNERS AND CHANNELS

NAIL ON THE TOP PLATE. After separating the top plate from the bottom plate (visible in the background), the top plate can be nailed to the studs, channels, and window and door assemblies. Drive a pair of 16d nails into each stud.

from the bottom plate, removing the 8d tack nails as you go. Leave the bottom p ate tacked to the floor for now. Nail the top plate first, using the bottom plate to keep the studs aligned. Move the top plate straight up to the upper ends of the studs. Don’t turn a top plate end for end as you move it into position or you’ll have a real mess. The exterior walls am be framed over the interior walls rather than fiat on the deck or slab (see the pholo at left). This is okay. The most important element in wall framing is to keep the frame reasonably straight and square on the floor. This is not difficult to do. Take vour time until you get it right.

Begin nailing studs to the plate at an out­side comer, making it flush with the edge. Drive a pair of 16d nails through the plate into each stud. You will find that consistently working either from left to right or from right to left has a natural feel. Over time, von will develop a rhythm to nailing studs that involves not just your hands and arms but your entire bodv.

If you are using a pneumatic nailer, always drive the bottom nail first. Then remove your
hand from the stud and drive the top nail. If you keep your hand in place while driving the top naif sooner or later you will miss and drive a nail into your hand. Unfortunately» I

learned this the hard wav.

/

W hen you come to a door or window opening, be especially careful to nail each king stud on the“X” mark next to the header loca­tion. Once nil the wall, king, and top cripple studs arc nailed to the top plate, pull up the bottom plate and begin nailing it n place, always paying attention to your layout marks. Repeat the process. Nail all wall members to the bottom plate just like you did with the top plate.

I always nail the blocks for a recessed, or in-wall, medicine cabinet while the wall is flat on the floor. At the “MC marking, hook your tape on the bottom plate and measure up 4 ft. and 6 ft. on the two studs on each side. Nail a flat block below the 4-ii. marks and above the б-ft. marks. This leaves a clear space of 2 ft., which is the height of a standard recessed medicine cabinet.