Mixing: Basic Information

Mixing the components of a bituminous mixture, proportioned by weight from hot – bins, in a batch asphalt plant takes place in a pugmill. Contemporary batch plants have pugmills of various sizes, usually from 1 ton to 8 tons. Despite the different sizes of pugmills and the resulting output of the plants, mixing time, by and large, remains at the same level for all plants (USACE Handbook, 2000). Determining the suitable amounts of materials to batch given the pugmill’s volume is quite a significant step

TABLE 9.1

Recommended Maximum Production Temperatures of an SMA Mixture for example binders according to various Regulations

Mixing: Basic Information Подпись: Germany ZTV Asphalt-StB 07 (Table 5) <190 <180
Подпись: EN 13108-5:2006 (Table 16) <190 <180 <170
Mixing: Basic Information
Подпись: <180 (PMB 25/55-55)
Mixing: Basic Information
Подпись: <190 (PMB 45/80-x)
Mixing: Basic Information

Maximum Mixture Temperature in Asphalt Plant (°С)

Note: PMB = Polymer modified binder.

and is one of the decisive actions undertaken during the plant’s calibration. The quantity of material intended for mixing in one cycle may neither be too large nor too small in comparison with the pugmill’s volume. In the case of an excessive charge of material, the mixing will be ineffective; the mixture will remain partially unmixed and the stabilizer will not be distributed throughout the mixture. An insufficient amount of material in the pugmill will result in throwing the mixture out of the mixing chamber instead of mixing it properly, an acceleration of the binder-aging process and, again, the potential of destroying the stabilizer.

In a drum-mix plant, components are continually delivered into a constantly mix­ing drum. Thus the control of the constituents’ proportions is exercised through the adjustment of the batching rate. The mixing time depends on the shifting rate of materials inside the drum, which can be affected by a variety of factors such as the length of the drum and the angle of the drum.

DOORS, WINDOWS, & STAIRS

Doors and windows are two of the few finish items that framers sometimes handle. It is important that time and care are taken to ensure they are installed in a proper, professional manner. Put your framing hammer in the toolbox and use, instead, a lighter, smoother-faced trim hammer and a nail set.

Exterior, pre-hung doors are the type covered in this chapter. They are the ones framers most commonly work with, and most of the skills involved in hanging them will carry over to the hanging of interior doors. The first door you hang on any job will give you the most difficulty. If you have more than one door to hang, do them one after the other; each door will go in a little easier than the one before.

Nail-flange windows and sliding glass doors will vary depending on the manufacturer. You will find here the basic principles of their installation. Use common sense and follow the directions provided, and you should have little trouble installing these units.

Stairs represent one of the more difficult challenges to a framer’s skill. As in roof framing, the geometry is a bit complicated, but taken step-by-step, the logic

soon becomes clear, leading to successful execution of the plans. There are many different stair designs. The stair layouts described in this chapter are typical. Be aware that the dimensions given on the plans do not always allow for enough headroom. Always check headroom and other dimensions by taking accurate on-site measurements. This chapter also contains instructions for laying out and framing circular stairs.

The instructions for installation of pre-hung doors, windows, sliding glass doors, straight stairs, and circular stairs are all presented in steps for easier understanding. A calculator is handy-some might say necessary-for finding the rise and tread dimensions when not given on the plans. Always double – or triple-check your calculations. Remember: measure twice, cut once. The finish floors at the top and bottom of stairs are often different. When cutting stair stringers, don’t forget to check the plans for such differences and then check the height of your top and bottom risers to allow for them.

One 16d galvanized casing nail at each hinge. Hinge

DO NOT SET NAILS

Door

View of door looking down from the top

АОЛ

Steps for Installation

1. READ INSTRUCTIONS

• Usually there are instructions that come with the door. Check the instructions over for anything you might need to know.

2. CHECK PLANS

• Check the building plans to find the direction of the door swing.

3. CHECK THE THRESHOLD

• Check the threshold for level. Shim under hinge jamb if necessary.

4. NAIL HINGE JAMB

• Nail hinge jamb tight to trimmer with one 16d galvanized casing nail at each hinge. Do not set nails. Plumb both directions. Shim behind jamb if necessary to obtain plumb or if door needs to be centered in opening.

Install window flashing. (See the following section.)

Set window in place.

Place temporary shims under bottom of window. Equalize space at top and bottom of window. Shims are usually 1/b" to W. Level windowsill.

Make gaps the same between window frame and trimmer on each side.

Nail top corners from outside.

Nail one bottom corner. (Do not set all the way.)

Place window slider in and check to see if the gap between the window slider and window frame is the same from top to bottom.

View From Inside

Header

8. If the gap is not equal, check both the rough opening and the window for square, and adjust accordingly.

9. Finish nailing. Make sure gap is equal top, bottom, and middle. (Do not nail top of the window.)

Minimum nailing:

Two nails on each side and one in the bottom. Increase the number of nails for larger windows. Use 8d nails.

Header flashing needs to be applied when weather-resistant barrier (house wrap) and siding are applied.

2. Attach 9" wide flashing at each jamb. Start flashing 8V2" above rough opening at header. Extend below and over flashing at sill. Do not attach where it extends over sill flashing.

Moisture penetration in buildings can cause rot in the structure. New and more extensive exterior rain protective systems have been developed and used to combat this problem. Some of these systems use a special type of water resistant barrier and self-adhesive flashing. Another system is the rainscreen. It provides a whole second layer of protection, typically by installing furring strips over the initial water – resistive barrier and then an outside siding material attached to the furring strips. These furring strips allow for ventilation and pressure equalization. These systems have not been standardized yet and so it is important to follow the specifications as outlined on the plans.

1. READ INSTRUCTIONS.

Read and follow carefully the instructions that come with the door. Never assume what you do not know.

2. SEAL THRESHOLD.

Use neoprene or similar sealing compound to seal the threshold.

3. INSTALL FLASHING.

The jamb flashing with sealer is installed using a method similar to the jamb flashing on windows.

4. PLACE DOOR.

Place the door in position.

5. CENTER TOP.

Center the top of the door in rough opening.

6. NAIL TOP CORNERS.

Nail each corner of the top of the door through nail flange. (Do not set nails.)

7. ADJUST DOOR.

Adjust the door frame so that the space between the door frame and wall trimmers is equal. Check for plumb with a level and adjust if necessary.

8. COMPLETE NAILING.

Close the door and latch it. Then nail off the sides using four 8d nails on each side. Do not nail top of door.

9. ADJUST DOOR.

Adjust the slider part of the door if necessary. Usually there is an adjustment screw at the bottom of the door. Tighten this screw to close a gap between the door and the jamb at the top of the door, or loosen to increase the gap.

10. TIGHTEN SCREWS.

If screws come with the door, shim and tighten screws in the sides and bottom. Use pre-drilled holes.

The three main dimensions in stair building are for risers, treads, and headroom. The riser height and the tread width are usually given on the plans. You can generally use the tread width given on the plans. The riser height, however, is often not accurate enough to use.

Stair Installation Steps

1. MEASURE HEIGHT.

Measure the height of the stairwell from finish floor to finish floor.

2. FIND RISER HEIGHT.

Divide the height of the stairwell by the number of risers shown on the plan to determine the riser height. Be careful to consider the finish floor heights, which may differ top and bottom.

3. FIND TREAD WIDTH.

Check plans for tread width.

4. CHECK HEADROOM.

Chalk a line from edge of nosing at top of stairs to edge of nosing at bottom of stairs. (See “Checking Stair Headroom" later in this chapter.) Check for minimum clearance of 6′-8" to finish straight up from line to bottom of headroom.

5. MARK AND CUT STRINGERS.

(See “Marking Stair Stringers" later in this chapter.")

6. CUT.

Cut stringer spacers, treads, and risers.

7. NAIL STRINGER SPACER.

Nail stringer spacer to stringer. Spacer leaves clearance for applying wall finish.

8. SET STRINGERS.

a. At top deck, measure down riser height plus tread thickness and mark for top of stringer.

b. Set stringers to mark.

c. Check stringers for level by placing a tread on top and bottom and checking level, side to side, and front to back.

d. Adjust stringers for level.

e. Nail stringers.

9. NAIL RISERS.

10. GLUE AND NAIL TREADS.

Production process

Suppose that we have already developed the job mix formula and that well-perform­ing batching devices, a screen deck, balances, and so on are at our disposal. Then we are ready to start production. A common occurrence with starting up an asphalt plant is the instability of the mixture temperature during the first production period. Therefore one should take into account that some batches will be underheated, while others will be slightly overheated. Such waste material should be rejected.

9.3.1 SMA Production Temperature

Two components of an SMA mixture must be heated—the aggregate and the binder. This heating is aimed at (1) eliminating moisture from the aggregate to a level that enables the proper coating of the aggregate grains and (2) maintaining the appropri­ate temperature of the mixture delivered to the laydown site, which allows for its proper placement and compaction. The coating temperature is directly related to the viscosity of the chosen binder. The harder the binder or the more highly modified the binder is, the higher the production temperature must be. That is why the SMA production temperature is most often specified as a function of the type of binder.

The SMA production temperature has been diversely defined in different coun­tries in the following manner: [56]

reveal data and ensure substantially uniform conditions for SMA produc­tion; EN standard 13108-5 (which applies only to unmodified binder) is a good example of such a document.

• Variant 2—the manufacturer of the binder discloses information on the rec­ommended production temperature; this method has been used for modi­fied and special binders.

• Variant 3—the viscosity range of the binder is used as the basis for the inde­pendent determination of the production temperature; in this case the vis­cosity-temperature relationship should be defined to allow determination of the range of temperatures that produces the needed binder viscosity.

An overview of SMA production temperatures according to selected documents is displayed in Table 9.1. A wide range of temperatures is specified in this table. One should remember that each increase of the mixing temperature enhances the risk of binder-mastic draining off the aggregate while also increasing the binder aging. The classic draindown test with Schellenberg’s method is carried out at 170°C, producing incomplete information about its behavior at higher temperatures. That is why it is a good idea to conduct another draindown test at a higher temperature that reflects the possible SMA production temperature (see Chapter 8).

SITE-BUILT FIXED WINDOWS

Storm sash made today are usually fitted to aging single-glazed windows. The storm sash protects the existing window from the weather and also improves the thermal performance of the window.

Usually made of aluminum, storm sash are custom fit to the exterior face of the existing window. Many are operable from the interior and are fitted with screens. Depending on how they are installed, storm sash can either significantly extend the useful life of old windows or actually contribute to their deterioration. A proper installation depends on numerous factors including the climate and the detailing of the original window.

SITE-BUILT FIXED WINDOWS

New custom wood windows can be manufactured with single glazing if fitted with storm sash. This can be useful for historic work or when attempting to make simple inexpensive sash for a microclimate that requires them. The storm sash provide the thermal performance required by code at the same time they protect the most precious part of the assembly—the sash itself—from the weather. Storms located at fixed sash can be left in place year-round, while storms at operable windows can be exchanged for screens during the summer.

SITE-BUILT FIXED WINDOWSWALLS

Doors

SITE-BUILT FIXED WINDOWS

HEAD

Traditional Exterior Door

Modern doors have been derived from traditional prototypes; they are better insulated and better sealed, and usually require less maintenance than their ances­tors. Exterior hinged doors are made of wood (ply­wood, composite, or solid wood), fiberglass (fiberglass skin over a wood frame with a foam core), or insulated steel. Wood is the most beautiful, fiberglass the most durable, steel the most inexpensive.

Most exterior doors swing inward to protect them from the weather. Nearly all manufacturers sell their doors prehung (hinged to a jamb and with exterior casing attached). Sills and thresholds are the most vari­able elements in manufactured prehung doors. Most doors come with an extruded metal sill and integral threshold, which is installed on top of the subfloor (see 100B). Wood sills must be thicker than metal for strength, so they work best with finish flooring materials that are 3/4 in. thick or more (see sill drawing at right).

Because of the torsional forces exerted by the hinges on the jamb when the door is open, doors that swing need to have their jambs fastened directly and securely to the buildings frame. The best way to accomplish this is to nail the jamb directly to the supporting stud, using shims to make the jamb plumb. It is common practice to attach a prehung door through the casing with long screws through the hinge and jamb into the stud.

Concluding Remarks

Road-related pollution sources include traffic and cargo, pavement and embank­ment materials, road equipment, maintenance and operation, and external sources. Road and traffic pollutants having received the greatest attention include heavy met­als (e. g. from vehicle corrosion, cargo spills and road equipment), hydrocarbons (from fuels, lubricants and bitumen), nutrients (generated from motor exhausts), particulates (from pavement and exhausts) and de-icing salt. Runoff, splash/spray and seepage through the road construction and the soil are major transport routes of pollutants from the road to the environment.

Pollutant transport through road materials and soils in the road environment is governed by the same physical processes as those occurring in soils elsewhere. During their downward transport, contaminants in the aqueous phase interact with the solid phase. For mass transport in saturated media, diffusion, advection and dis­persion are the major processes. Mass transport in unsaturated soil strongly depends on soil-moisture distribution inside the pores. After prolonged dry periods, the first flush of runoff often contains large quantities of pollutants accumulated on the road surface. Long-lying snow close to roads accumulates traffic pollutants.

In road soils, like elsewhere, the most significant chemical processes govern­ing the transport of substances including pollutants are sorption/desorption, dis – solution/precipitation and exchange reactions. Sorption of substances in the liq­uid form on soil particles greatly influences pollutant solubility and transport in soils. Redox conditions and acidity (pH) largely regulate the solubility and thus the mobility of heavy metals. Many heavy metals are more mobile under acidic conditions.

Roadside vegetation influences the transport of traffic contaminants through air, water and soil. Plants close to heavily trafficked roads accumulate traffic pollutants such as heavy metals. Heavy metals, organics, de-icing salt and other toxic sub­stances disturb biological processes in plants, animals, micro-organisms and other biota and may contaminate water bodies and the groundwater.

European legislation puts increasingly strong demands on the protection of water against pollution. Road-keepers are responsible for ensuring that the construction and use of roads is not detrimental to the quality of natural waters.

Strategies for the protection of the environment from road and traffic pollutants should primarily be directed towards limiting the generation of pollutants. As a complement to source-based measures, mitigation measures aim at reducing the dispersal of pollutants to the roadside environment and detrimental effects on soil, water and biota. Principles of road and traffic pollution prevention and mitigation include both technical and biological methods some of which are briefly outlined in Chapter 12.

Including consideration of measures for environmental protection at an early planning stage is much more cost efficient than retrofitting measures and installa­tions afterwards. To judge the need for prevention and mitigation measures, chemi­cal and biological characterization of soil and water is often required. Principles for the sampling and analysis are briefly described in Chapter 7.

The issue of contaminants in the environment is a very large subject and it is not possible within a few chapters to fully address the issues, even limiting the coverage to highway-related topics. Readers who want to explore further will find no shortage of reading material and can readily study the underlying science in much more detail than has been possible in this chapter (e. g. Fetter, 1993; Rand & Petrocelli, 1995; Charbeneau, 1999).

REMAINING TABLES

The remaining tables are different in content, but the procedures for using them are the same. Once you know the number of bedrooms and bathrooms for a dwelling, you can quickly and easily determine the minimum require­ments for a water heater. You have just seen how simple the tables are. When you have a water heater to size, just refer to the tables in this chapter (Fig. 7.4, to 7.10) or the tables in your local codebook.

Number of bedrooms

2

3

4

5

Storage capacity (gallons)

30

40

40

50

Input in Btuh

36,000

36,000

38,000

47,000

Draw (gallons per hour)

60

70

72

90

Recovery (gallons per hour)

30

30

32

59

FIGURE 7.4 ■ Water heating sizing table for gas heaters (minimum recommendations). Assume 2 to 21/2 bathrooms.

Number of bedrooms

2

3

4

5

Storage capacity (gallons)

40

50

50

66

Input in Btuh

4.5 KW

5.5 KW

5.5 KW

5.5 KW

Draw (gallons per hour)

58

70

72

88

Recovery (gallons per hour)

18

22

22

22

FIGURE 7.5 ■ Water heating sizing table for electric heaters (minimum recommendations). Assume 2 to 21/2 bathrooms.

Number of bedrooms

2

3

4

5

Storage capacity (gallons)

30

30

30

30

Input in Btuh

70,000

70,000

70,000

70,000

Draw (gallons per hour)

89

89

89

89

Recovery (gallons per hour)

59

59

59

59

FIGURE 7.6 ■ Water heating sizing table for oil-fired heaters (minimum recommendations). Assume 2 to 21/2 bathrooms.

Number of bedrooms

3

4

5

6

Storage capacity (gallons)

40

50

50

50

Input in Btuh

38,000

38,000

47,000

50,000

Draw (gallons per hour)

72

82

90

92

Recovery (gallons per hour)

32

32

40

42

FIGURE 7.7 ■ Water heating sizing table for gas heaters (minimum recommendations). Assume 3 to 31/2 bathrooms.

Number of bedrooms

3

4

5

6

Storage capacity (gallons)

50

66

66

80

Input in Btuh

5.5 KW

5.5 KW

5.5 KW

5.5 KW

Draw (gallons per hour)

72

88

88

102

Recovery (gallons per hour)

22

22

22

22

FIGURE 7.8 ■ Water heating sizing table for electric heaters (minimum recommendations). Assume 3 to 3V2 bathrooms.

Number of bedrooms

3

4

5

6

Storage capacity (gallons)

59

59

59

59

Input in Btuh

70,000

70,000

70,000

70,000

Draw (gallons per hour)

89

89

89

99

Recovery (gallons per hour)

59

59

59

59

FIGURE 7.9 ■ Water heating sizing table for oil-fired heaters (minimum recommendations). Assume 3 to 3V2 bathrooms.

Подпись: PLUMBER'S AND PIPE FITTER'S CALCULATIONS MANUAL

Column 1

Column 2

Buildings of ordinary tightness

Buildings of unusually tight construction

Condition

Size of opening or duct

Condition

Size of opening or duct

Appliance in unconfined2

space

May rely on infiltration alone.

Appliance in unconfined2 space:

Obtain combustion air from outdoors or from space freely communicating with outdoors.

Provide two openings, each having 1 sq. in. per 5,000 Btu/h input.

Appliance in confined4 space

1. All air from inside building

Provide two openings into enclosure each having one square inch per 1,000 Btu/h input freely communicating with other unconfined interior spaces. Minimum 100 sq. in. each opening.

Appliance in confined4 space:

Obtain combustion air from outdoors or from space freely communicating with outdoors.

1. Provide two vertical ducts or plenums: 1 sq. in. per 4,000 Btu/h input each duct or plenum.

2. Provide two horizontal ducts or plenums: 1 sq. in. per 2,000 Btu/h input each duct or plenum.

3. Provide two openings in an exterior wall of the enclosure: each opening 1 sq. in per 4,000 Btu/h input.

4. Provide one ceiling opening to ventilated attic and one vertical duct to attic: each opening 1 sq. in. per 4,000 Btu/h input.

2. Part of air from inside building

Provide two openings into enclosure3 from other freely communicating unconfined2 interior spaces, each having an area of 100 sq. in. plus one duct or plenum opening to outdoors having an area of 1 sq. in. per 5,000 Btu/h input rating.

3. All air from outdoors: Obtain from outdoors or from space freely communicating with outdoors.

Use of any of the methods listed for confined space in unusually tight construction as indicated in Column 2.

5. Provide one opening in enclosure ceiling to ventilated attic and one opening in enclosure floor to ventilated crawl space: each opening 1 sq. in. per 4,000 Btu/h input.

’For location of opening, see Section 1307(c).

2As defined in Section 122,

3When the total input rating of appliances in enclosure exceeds 100,000 Btu/h, the area of each opening into the enclosure shall be increased 1 sq. in. for each 1,000 Btu/h over 100,000,

4As defined in Section 104(h).

 

FIGURE 7.10 ■ Size of combustion air openings or ducts for gas-or liquid-burning water heaters. [Courtesy of Uniform Plumbing Code)

Подпись: WATER PUMPS

ome plumbers work their entire careers without ever having to know anything about water pumps. Other plumbers deal with pumps on a fre­quent basis. The difference is where the plumbers work. I’ve never worked in New York City, but I suppose there are not many water pumps to be installed or serviced. But where I live, in Maine, there are more homes served by private water wells than you can shake a stick at. When I lived in Virginia, there were plenty of water pumps, too. Some of the pumps are jet pumps and others are submersible pumps. The two are very different, even though they do the same job.

Jet pumps are at their best when used in conjunction with shallow wells, with depths of say 25 feet or less. Two-pipe jet pumps can be used with deep wells, but a submersible pump is usually a better option for deep wells. Sizing water pumps and pressure tanks is routine for some plumbers and foreign to others. This chapter is going to give you plenty of data to use when working with pump systems.

The illustrations I have to offer you in this chapter are detailed and self­explanatory. I believe that you will be able to use this chapter as a quick-ref­erence guide to most of your pump questions. Look over the following illus­trations and you will find data on jet pumps, submersible pumps, and pressure tanks. The data will prove very helpful if you become involved with the in­stallation, sizing, or repair of water pumps (Figs. 8.1 to 8.37).

135

This check list is intended to bdp in making reliable submersible pump installations. Other data for specific pumps may be needed.

 

1. Motor Inspection

___ Л. Verify thai lire model. HP or KW. voltage, phase

and heitz on the motor nameplate match the installation requirements. Consider any special comision resistance required.

___ B, Check that I he motor lead assembly ts tight in Uie

motor and that the motor and lead are not damaged.

___ C. Test insulation resistance using a 500 or l(MX) volt

DC inegohmmeier, from each lead wire to the motor frame, Resistance should be at least 20 megohms, motor only, no cable.

D. Keep a record of motor model number, HP or KW, voltage, date code and serial number,

2. Pump Inspection

___ A. Check that the pump rating matches the motor, and

that it is not damaged.

___ B. Verily that the pump shaft turns freely.

3. Pump/Motor Assembly

___ A. If not yet assembled, check that pump and motor

mounting faces are free from dirt and uneven paint

thickness.

___ B, Assemble the pump and motor together so their

mourning faces are in contact, then tighten assembly holis or nuts evenly to manufacturer specifications.

И it is visible, chuck dial the pump shaft is raised slightly by assembly to the motor, conlilining impeller running clearance.

___ C. If accessible, check that the pump shaft rums freely.

___ D. Assemble the pump lead guard over the motor

leads. Do not eui nr pinch lead wire during assembly or handling of the pump during installation.

4. Power Supply and Controls

__ A. Verify that the power supply voltage, here?., and

KVA capacity malch motor requirements.

B, Use a matching control box with each single phase three wire motor.

___ C. Check that the electrical installation arid controls

meet all safety regulations and match the motor requirements, including fuse or circuit breaker size and motor overload protection. Connect all metal plumbing and electrical enclosures to (he power supply ground in prevent shock hazard, Comply with National and local codes.

5. Lightning and Surge Protection

___ A. Use properly rated surge (lightning) arresiors on all

submersible pump installations unless the installa­tion is operated directly from an individual gen­erator and/or is not exposed to surges. Motors 5HP and smaller which are marked “Equipped with Lightning Arrestors’contain internal arrestors.

 

B. Ciround all above ground arrestors with copper wire directly to the motor frame. or to metal drop pipe or casing which reaches below the well pumping level, Connecting to a ground rod does not provide good surge protection.

 

6. Electrical Cable

___ A. Use cable suitable for use in water, sized to carry’ the

motor current without overheating in water and in air, and complying with local regulations. To maintain adequate voltage at die motor, use lengths no longer than specified in die motor manufacturer s cable charts,

___ B. Include a ground wire to liie pump if required by

codes or. surge protection, connected lo the power supply ground Always ground any pump operated outside a drilled well.

7. Well Conditions

___ A, For adequate cooling, motors must have at least the

water flow shown on ils nameplate. If well conditions and construction do not assure this much water How will always come from below the motor, use a flow’ sleeve as shown in the Application, Installation & Maintenance Manual

___ B. If water temperature exceeds JO degrees C <86 T).

reduce live motor loading or increase the How rate to prevent overheating, as specified in the Application. Installation & Maintenance Manual.

B. Pump/Motor Installation

___ A. Splice motor leads lo supply cable using electrical

grade solder or compression connectors, and carefully insulate each splice with watertight tape or adhesive-lined shrink tubing, as shown in motor or pump installation data.

___ B. Support the cable to the delivery pipe every 10 feel

(3 meters) with straps or tape strong enough to prevent sagging. Use pads between cable and any metal straps.

___ C. A check valve in the delivery pipe is recommended,

even though a pump may be reliable without one. More than one check valve may be required, depending cm valve rating and pump setting. Install the lowest check valve below the lowest pumping level of the well, lo avoid hydraulic shocks which may damage pipes, valve or motor.

___ D. Assemble all pipe joints as lightly as practical, to

prevent unscrewing from motor torque. Recommended torque is at least 10 pound feet per HP (2 mcter-KG per KWi.

___ E. Set the pump fur enough below the lowest pumping

level to аччигс the pump inlet will always have at least the Net Positive Suction 1 lead |NPSI l) specified by the pump manufacturer, but at least 11) leet (3 meters) from the bottom of the well lo allow for sediment build up.

 

___ F. Cheek, insulation resistance from dry motor cable

ends to ground as the pump is installed, using а 5Ш or KM) volt DC megohm meter. Resistance may drop gradually as mere cable enters the water, but any sudden drop indicates possible cable, splice or motor lead damage. Resistance should meet motor manufacturer data,

9. After Installation

___ A. Check all electrical and waterline connections and

parts before starting the pump, Make sure water delivery will not wd any electrical parts, and recheck that overload protection in three phase controls meets requirements.

___ B. Strut the pump and check motor amps and pump

delivery. If normal, continue to run the pump until delivery is clear. If three phase pump delivery is low, it may be running backward because phase, sequence is reversed. Rotation may be reversed (with power off) by interchanging any two motor lead connections to the power supply.

___ C. Connect three phase motors for current balance

within 5% of average, using motor manufacturer instructions. Unbalance over 5c7c will cause higher motor temperatures and may cause overload trip, vibration, and reduced life.

___ D. Make sure that starling, running and stopping cause

no significant vibration or hydraulic shocks.

___ E. A Iter at least 15 minutes running, verify that pump

output, electrical input, pumping level, and other characteristics arc stable and as specified.

Date____________________ Filled In By

10. Installation Data

Well Identification_________________________________ _________________________________________

Check By ____________________________________ _

Date___ /____ (_____

Notes __________________________________________

 

KM A No.

 

REMAINING TABLES
REMAINING TABLES

Pump Inlet Setting___

Flow Sleeve: No

 

_ Yes. Dia.

 

Casing Depth______ Jt

□ Well Screen □ Perforated Casing From__ to_________ ft. &__ to________ ft-

 

– Well Depth_

Form No. 2207 2AM

 

REMAINING TABLES

Average water requirements for general

service around the home and farm

Each person per day, for all purposes

75 gal.

Each horse, dry cow, or beef animal

12 gal.

Each milking cow

35 gal.

Each hog per day

4 gal.

Each sheep per day

2 gal.

Each 100 chickens per day

4 gal.

Average amount of water required by

various home and yard fixtures

Drinking fountain, continuously flowing

50 to 100 gal. per day

Each shower bath

Up to 30 gal. @ 3-5 gpm

To fill bathtub

30 gal.

To flush toilet

6 gal.

To fill lavatory

2 gal.

To sprinkle V4" of water on each 1000

square feet of lawn

1б0 gal.

Dishwashing machine — per load

7 gal. @ 4 gpm

Automatic washer —per load

Up to 50 gal. @ 4-6 gpm

Regeneration of domestic water softener

50-100 gal.

Average flow rate requirements by

various fixtures

(gpm = gal. per minute; gph =

gal. per hour)

Shower

3-5 gpm

Bathtub

3-5 gpm

Toilet

3 gpm

Lavatory

3 gpm

Kitchen sink

2-3 gpm

У2” hose and nozzle

200 gph

1/4" hose and nozzle

300 gph

Lawn sprinkler

120 gph

FIGURE 8.3 ■ Average water requirements for general service. (Courtesy of McGraw-Hill)

Each horse

Approx. Gallons Per Day

12

Each producing cow

15

Each nonproducing cow

12

Each producing cow with drinking cups

30-40

Each nonproducing cow with drinking cups

20

Each hog

4

Each sheep

2

Each 100 chickens

4-10

Yard fixtures:

Vi-inch hose with nozzle

200

M-inch hose with nozzle

300

Bath houses

10

Camp

Construction, semipermanent

50

Day (with no meals served)

15

Luxury

100-150

Resorts (day and night, with limited plumbing)

50

Tourists with central bath and toilet facilities

35

Cottages with seasonal occupancy

50

Courts, tourists with individual bath units

50

Clubs

Country (per resident member)

100

Country (per nonresident member present)

25

FIGURE 8.4 ■ Daily water requirements. (Courtesy of McGraw-Hill)

Dwellings

Luxury

Multiple family, apartments (per resident)

Rooming houses (per resident)

Single family Estates _

Factories (gallons/person/shift)

Institutions other than hospitals Hospitals (per bed)

Laundries, self-serviced (gallons per washing, i. e., per customer)

Motels

With bath and toilet (per bed space)

Parks

Overnight with flush toilets Trailers with individual bath units Picnic

With bath houses, showers, and flush toilets With only toilet facilities (gal./picnicker) Restaurants with toilet facilities (per patron)

Without toilet facilities (per patron)

With bars and cocktail lounge (additional quantity) Schools Boarding

Day with cafeteria, gymnasiums and showers Day with cafeteria but no gymnasiums or showers Service stations (per vehicle)

Stores (per toilet room)

Swimming pools Theaters

Drive-in (per car space)

Movie (per auditorium seat)

Workers

Construction (semipermanent)

Day (school or offices per shift)

 

75

60

50

75

100-150

15-35

75-125

250-400

50

100

25

50

20

10

10

3

2

50-70

25

20

10

400

10

5

5

50

15

 

Providing an adequate water supply provides for a healthy family and higher production from livestock. Assuming the total daily requirement is calculated to be 1200 gpd (gallons per day), a pump would be selected for a capacity of 10 gpm (gallons per minute) based on the following formula:

 

1200 gph t 2 equals 600 gph (gal. per hr.)

 

REMAINING TABLES

FIGURE 8.4 ■ (Continued) Daily water requirements. (Courtesy of McGraw-Hill)

 

REMAINING TABLES

Engineering Data
Drop Cable Selection Chart

Single-phase, two or three-wire cable, 60 Hz (service entrance to motor)

 

REMAINING TABLES
REMAINING TABLES

REMAINING TABLES

Engineering data

Formulas and conversion factors
Centrifugal pumps

 

REMAINING TABLES

К

El

d

 

Volume

1 U. S, gallon – 231 cu. in,

1 U. S. gallon =■ 3-785 liters 1 Imperial gallon *1.2 U. S.

gallons

1 barrel (oil) я 42 U. S, gallons 1 cubic foot * 7.48 U. S, gallons

1 acre foot = 325,850 U. S.

gallons

1 cubic meter * 264,2 U. S.

gallons

Weight

1 U. S. gallon water weighs 8,35 lbs.

1 cubic foot water weighs

 

Head

1 lb. per sq. in. = 2.31 ft. of water 1 foot of water = 0-433 lbs. per sq. in. 1 inch of mercury = 1,133 ft. of water 1 atmosphere (sea level) – 14.7 lbs, per sq. in.

1 kilogram per sq. centimeter * 14,22 lbs. per sq. in.

Length

1 meter » 3.28 feet – 39.37 inches Power

1 horsepower = 745-7 watts 1 kilowatt * 1000 watts 1 kilowatt = 1.341 HP 100 boiler HP requires 7 gpm feed water approximately.

 

FIGURE 8.6 ■ Formulas and conversion factors for centrifugal pumps. (Courtesy of McGraw-Hill)

 

REMAINING TABLES

REMAINING TABLES

system

 

REMAINING TABLES

xtsll~x~trol

 

REMAINING TABLES

system

 

REMAINING TABLES

Relief valve

 

REMAINING TABLES

Submersible pump

 

REMAINING TABLES

REMAINING TABLES

FIGURE 8.7 ■ Pressure tank in use with a submersible pump. (Courtesy of McGraw-Hill)

REMAINING TABLES

О 1 2 3 456789 10 11 12

U. S. gallons per minute

FIGURE 8.8 ■ Performance rating chart for pump with 5 gallon-per- minute output. (Courtesy of McGraw-Hill)

REMAINING TABLES

FIGURE 8.9 ■ Performance rating chart for pump with 10 gallon-per- minute output. (Courtesy of McGraw-Hill)

1000

 

REMAINING TABLES

800

 

700

 

400

 

200

 

100

 

U. S. gallons per minute

 

FIGURE 8.10 ■ Performance rating chart for pump with 13 gallon-per – minute output. (Courtesy of McGraw-Hill)

REMAINING TABLES

 

REMAINING TABLES

REMAINING TABLES

REMAINING TABLES

800

 

700

 

400

 

200

 

100

 

U. S. gallons per minute

 

REMAINING TABLES

REMAINING TABLES

FIGURE 8.12 ■ Performance rating chart for pump with 25 gallon-per – minute output. (Courtesy of McGraw-Hill)

Output In gallons per hour

Discharge pressure 0 P. S.I.

 

REMAINING TABLES

Impeller

Pres, switch

Suction

Discharge

Shipping

Model no.

HP

Volts

material

setting

pipe size

size

weight

8130

Уз

115

Plastic

20-40

1У4”

■1/4"

46 lbs.

8131

Уз

115

Brass

20-40

1У4"

48 lbs.

8150

y2

115/230

Plastic

20-40

1У4”

‘■’A"

48 lbs.

8151

y2

115/230

Brass

20-40

1У4"

50 lbs.

8170

3/4

115/230

Plastic

30-50

IV*’

%"

50 lbs.

8171

3/4

115/230

Brass

30-50

1У4"

%"

52 lbs.

8110

1

115/230

Plastic

30-50

1У4”

52 lbs.

8111

1

115/230

Brass

30-50

1У4"

53 lbs.

FIGURE 8.14 ■ Performance ratings for jet pumps. (Courtesy of McGraw-Hill)

Подпись: PLUMBER'S AND PIPE FITTER'S CALCULATIONS MANUAL
Подпись: Impeller Pres, switch Suction Twin type Shipping Model Model HP Volts material setting pipe size drop pipe weight 1550 1050 Vz 115/230 Brass 30-50 1%" 1" x l'A” 65 lbs. 1575 1075 3/4 115/230 Brass 30-50 1У4" 1" X ІУ4" 71 lbs. 1575SW 1075SW % 115/230 Brass 30-50 1У." Г x 1УТ 66 lbs. 1510 1010 1 115/230 Brass 30-50 1У4" Г x l'A" 74 lbs. 1510SW 1010SW 1 115/230 Brass 30-50 1У4" 1" x I'A” 67 lbs. 1515SW 1015SW l‘/2 115/230 Brass 30-50 1У4” Г X l'A" 72 lbs.

FIGURE 8.15 ■ Performance ratings for multi-stage pumps. [Courtesy of McGraw-Hill)

REMAINING TABLES

FIGURE 8.16 ■ Shallow-well performance chart. (Courtesy of McGraw-Hill)

REMAINING TABLES

FIGURE 8.17 ■ A typical jet-pump set-up. (Courtesy of McGraw-Hill)

REMAINING TABLES

system

 

REMAINING TABLES

Pump

 

REMAINING TABLES

Dram

 

REMAINING TABLES
REMAINING TABLES

REMAINING TABLES

REMAINING TABLES

FIGURE 8.18 ■ A jet pump mounted on a pressure tank with a pump bracket. (Courtesy of McGraw-Hill)

REMAINING TABLES

FIGURE 8.19 ■ A typical piping arrangement for a jet pump. (Courtesy of McGraw-Hill)

REMAINING TABLES

FIGURE 8.20 ■ Bracket-mounted jet pump on a horizontal pressure tank. (Courtesy of McGraw-Hill)

REMAINING TABLES

FIGURE 8.21 ■ Small, vertical pressure tank installed above pump. (Courtesy of McGraw-Hill)

REMAINING TABLES

FIGURE 8.22 ■ Small, vertical pressure tank installed above pump. (Courtesy of McGraw-Hill)

REMAINING TABLES

REMAINING TABLESFIGURE 8.24 ■ An underground installation of a pressure tank. (Courtesy of McGraw-Hill)

REMAINING TABLES

REMAINING TABLES

FIGURE 8.25 ■ In-line pressure tank. (Courtesy of McGraw-Hill)

 

Stand models

 

REMAINING TABLES

FIGURE 8.26 ■ Stand-type pressure tank. (Courtesy of McGraw-Hill)

 

REMAINING TABLES

REMAINING TABLES

Model

Dimensions

Total

1,5/3,0 bar

2,0/3,5 bar

2,5/4,0 bar

System

Precharge

Shipping

No.

Diameter

Height

Volume

Drawdown

Connection

Pressure

Wt./Vol.

mm

mm

Ltr

Liter

Liter

Liter

FT

bar

KG/m3

WX 2,6

156

228

2.6

1,0

0,9

0,8

3/4

1,5

1,0/,005

WX4

156

302

4,1

1,5

1,4

1,2

3/4

1.5

1,5/,007

WX8

200

320

8

3,0

2.6

2,4

3/4

1,5

2,3/,02

WX 18

280

380

18

6,7

6,0

5,4

3/4

1,5.

4,1 / ,03

WX33

280

630

33

12,4

10,9

9,9

3/4

1,5

6,8 / ,05

 

REMAINING TABLES

FIGURE 8.27 ■ Specifications for in-line pressure tanks. (Courtesy of McGraw-Hill)

Подпись: WATER PUMPS ■ 157

10 bar series

 

REMAINING TABLES

Mode

 

WL 1855

 

560

 

805

 

REMAINING TABLES

801

 

REMAINING TABLES

560

 

805

 

180

 

560

 

1240

 

560

 

1700

 

300

 

750

 

1880

 

600

 

750

 

2340

 

800

 

1000

 

1960

 

1000

 

000

 

2740

 

600

 

2493

 

1200

 

2000

 

16 bar series

 

REMAINING TABLES

560

 

805

 

560

 

1240

 

560

 

1700

 

300

 

750

 

1880

 

600

 

750

 

2340

 

800

 

1801-20001

 

1960

 

1000

 

1000

 

2740

 

1600

 

REMAINING TABLES

2000

 

2493

 

REMAINING TABLES

REMAINING TABLES

1,5/3,0 bar

2,0/3,5 bar

2,5/4,0 bar

System

Connection

Precharge

Pressure

Shipping

Wt./Vol.

Liter

Drawdown

Liter

Liter

FT

bar

KG /m3

30

27

24

2

3,5

59 / ,25

68

60

54

2

3,5

83 / ,39

113

99

90

2

3,5

155/,53

225

198

180

2

3,5

285/1,06

300

264

240

2

3,5

360/1,32

375

330

300

3

3,5

400 /1,96

600

528

480

3

3,5

540/2,74

750

660

600

3

3,5

780 / 3,59

30

27

24

2

3,5

59/,25

68

60

54

2

3,5

83 / ,39

113

99

90

2

3.5

155/,53

225

198

180

2

3,5

285 /1,06

300

264

240

2

3,5

360 /1,32

375

330

300

3

3,5

400 /1,96

600

528

480

3

3.5

540/2,74

750

660

600

3

3,5

7890/3,59

30

27

24

2

3,5

64 / ,25

68

60

54

2

3,5

102/,39

113

99

90

2

3,5

220 / ,53

225

198

180

2

3,5

400/1,06

300

264

240

2

3,5

505/1,32

375

330

300

3

3,5

560 / 1,96

600

528

480

3

3,5

756/2,74

750

660

600

3

3,5

1330/3,5

FIGURE 8.28 ■ (Continued) Specifications for pressure tanks with replaceable bladder designs. (Courtesy of McGraw-Hill)

REMAINING TABLES

FIGURE 8.29 ■ Detail for a tank-tee set-up. (Courtesy of McGraw-Hill)

 

Dimensions

Total

Max.

Drawdown

ShipplRQ

Model

Diameter

Height

Volume

Accept.

2W40

30/50

40/50

m (Vo i. >

No.

(ini)

(in)

(tali)

Factor

(gala)

(gall)

(gala)

H>i feu 44>

WX-103-PS

12 V2

11 VA

8.6

028

3 1

2.7

22

20(2.4}

WX 200-PS

17 W

15 *8

140

0.31

5.2

43

38

29(4 0)

Precharge Pressure is 30 PSIG and Sys. Conn, is *4“ NPTM Filling lor 103-PS and i" NPTF Coupling lor 2Q0-PS. Maximum Working Pressure is 100 PSIG and Maximum Working Temperalure is 200" F.

 

FIGURE 8.30 ■ Pump-stand type of pressure tank. (Courtesy of McGraw – Hill)

 

REMAINING TABLES

REMAINING TABLESREMAINING TABLES

REMAINING TABLES

FIGURE 8.31 ■ Underground pressure tank specifications. (Courtesy of McGraw-Hill)

REMAINING TABLES

When the pump starts, water enters the WELL-X-TROL as system pressure passes the minimum pressure precharge. Only usable water is stored.

 

WELL-X-TROL has a sealed-in air chamber that is pre-pfessurized before it leaves our factory. Air and water do not mix eliminating any chance of “waterlogging” through loss of air to system

 

REMAINING TABLES

When water is demanded, pressure in the air chamber forces water into the system. Since WELL-X-TROL does not waterlog and consistently delivers the maximum usable water, minimum pump starts are assured.

 

FIGURE 8.32 ■ How diaphragm pressure tanks work. (Courtesy of McGraw-Hill)

 

Maximum starts per 24 hr. day

Motor rating

Single phase

Three phase

Up to 3A hp

300

300

1 hp thru 5 hp

100

300

7 У2 hp thru 30 hp

50

100

40 hp and over

100

 

FIGURE 8.33 ■ Recommended maximum number of times a pump should start in a 24-hour period. (Courtesy of McGraw-Hill)

 

REMAINING TABLES

O’*

ы

 

Подпись: PLUMBER’S AND PIPE FITTER’S CALCULATIONS MANUAL

Operating pressure—psig

discharge 20/40 30/50 40/60

rate gpm (approx.) 2.5

ESP I

ESP II

ESP I

ESP II

ESP I

ESP II

WX-104

WX-201

WX-104

WX-202

WX-104

WX-202

5

WX-201

WX-205

WX-202

WX-205

WX-202

WX-250

7

WX-202

WX-250

WX-203

WX-251

WX-205

WX-251

10

WX-203

WX-251

WX-205

WX-302

WX-250

WX-302

12

WX-205

WX-302

WX-250

WX-302

WX-251

WX-350

15

WX-250

WX-302

WX-251

WX-350

WX-251

WX-350

20

WX-251

WX-350

WX-302

(2JWX-251

WX-302

(2)WX-302

25

WX-302

(2JWX-302

WX-302

(2)WX-302

WX-350

(3)WX-251

30

WX-302

(2)WX-302

WX-350

(DWX-302

WX-350

(2)WX-350

35

WX-350

(DWX-302

WX-350

(DWX-350

(2)WX-350

(2JWX-251

(3)WS-302

40

WX-350

(DWX-350

(2)WX-350

(2)WX-251

(3)WX-302

(2)WX-302

(DWX-302

(2)WX-350

 

FIGURE 8.34 ■ Sizing and selection information for perssure tanks. (Courtesy of McGraw-Hill)

AFOSM reliability analysis for nonnormal correlated stochastic variables

For most practical engineering problems, parameters involved in load and re­sistance functions are correlated nonnormal random variables. Such distribu­tional information has important implications for the results of reliability com­putations, especially on the tail part of the distribution for the performance function. The procedures of the Rackwitz normal transformation and orthogo­nal decomposition described previously can be incorporated into AFOSM reliability analysis. The Ang-Tang algorithm, outlined below, first performs the orthogonal decomposition, followed by the normalization, for problems involv­ing multivariate nonnormal stochastic variables (Fig. 4.12).

The Ang-Tang AFOSM algorithm for problems involving correlated nonnor­mal stochastic variables consists of the following steps:

Step 1: Decompose correlation matrix Rx to find its eigenvector matrix Vx and eigenvalues Лх using appropriate techniques.

Step 2: Select an initial point x(r) in the original parameter space.

Step 3: At the selected point x(r), compute the mean and variance of the performance function W(X) according to Eqs. (4.56) and (4.43), respectively.

Step 4: Compute the corresponding reliability index во-) according to Eq. (4.8).

Step 5: Compute the mean pkN,(r) and standard deviation akN,(r) of the normal equivalent using Eqs. (4.60) and (4.61) for the nonnormal stochastic variables.

Step 6: Compute the sensitivity coefficient vector with respect to the per­formance function sz>,(r) in the independent, standardized normal z’-space, according to Eq. (4.68), with Dx replaced by DxN,(r).

Step 7: Compute the vector of directional derivatives a? (r) according to Eq. (4.67).

Step 8: Using во-) and a^ ,о) obtained from steps 4 and 7 , compute the location of solution point z(r +in the transformed domain according to Eq. (4.70).

Step 9: Convert the obtained expansion point z(r+1) back to the original pa­rameter space as

x (r + 1) = px, N,(r) + D x, N,(r) Vx ЛУ2 z (r +1) (4.73)

in which px, N,(r) is the vector of means of normal equivalent at solution point x(r), and Dx, N,(r) is the diagonal matrix of normal equivalent variances.

Step 10: Check if the revised expansion point x(r+1) differs significantly from the previous trial expansion point x (r). If yes, use the revised expansion point as the trial point by letting x(r) = x(r+1), and go to step 3 for another iteration. Otherwise, the iteration is considered complete, and the latest reliability index во) is used in Eq. (4.10) to compute the reliability ps.

Step 11: Compute the sensitivity of the reliability index and reliability with respect to changes in stochastic variables according to Eqs. (4.48), (4.49), (4.51), (4.69), and (4.58), with Dx replaced by D x, n at the design point x^.

One drawback of the Ang-Tang algorithm is the potential inconsistency be­tween the orthogonally transformed variables U and the normal-transformed space in computing the directional derivatives in steps 6 and 7. This is so be­cause the eigenvalues and eigenvectors associated with Rx will not be identical to those in the normal-transformed variables. To correct this inconsistency, Der Kiureghian and Liu (1985), and Liu and Der Kiureghian(1986) developed a
normal transformation that preserves the marginal probability contents and the correlation structure of the multivariate nonnormal random variables.

Suppose that the marginal PDFs of the two stochastic variables Xj and Xk are known to be f j (Xj) and fk (xk), respectively, and their correlation coefficient is pjk. For each individual random variable, a standard normal random variable that satisfies Eq. (4.59) is

Ф( Zj) = Fj (Xj) Ф( Zk) = Fk (Xk) (4.74)

By definition, the correlation coefficient between the two stochastic variables X j and Xk satisfies

Xj J j f Xk Jk

 

AFOSM reliability analysis for nonnormal correlated stochastic variables

G

 

Gk

 

(4.75)

 

Xj Xj f Xk ixk

Gk

 

fj, k (Xj, Xk) dxj dxk

 

AFOSM reliability analysis for nonnormal correlated stochastic variables

where xk and Gk are, respectively, the mean and standard deviation of Xk. By the transformation of variable technique, the joint PDF f j, k (Xj, Xk) in Eq. (4.75) can be expressed in terms of a bivariate standard normal PDF as dj dn

Подпись: fj ,k (Xj , Xk) = Ф (zj, Zk | Pjk )д X j d Xk d Zk d Zk d Xj d Xk

where ф(Zj, zk | pjk ) is the bivariate standard normal PDF for Zj and Zk having zero means, unit standard deviations, and correlation coefficient pjk, and the elements in Jacobian matriX can be evaluated as

AFOSM reliability analysis for nonnormal correlated stochastic variables Подпись: for j = k

dZk _ дф—^ЫУ] _ fk (Xk) dXk dXk Ф (Zk )

Then the joint PDF of Xj and Xk can be simplified as

fj I Xj, Xk) = HZ,,Zk |pjk) – ф^ Фф* 14.76)

Подпись: P jk = AFOSM reliability analysis for nonnormal correlated stochastic variables Подпись: xj Л Gj Подпись: xk /Xk Gk Подпись: Фjk (zj, Zk |pjk) dzj dzk Подпись: (4.77)

Substituting Eq. (4.76) into Eq. (4.75) results in the Nataf bivariate distribution model (Nataf, 1962):

in which Xk = F— 1 [Ф (Zk)].

Two conditions are inherently considered in the bivariate distribution model of Eq. (4.77):

1. According to Eq. (4.74), the normal transformation satisfies,

Zk — ф-^Fk (Xk)] for k — 1,2,…, K (4.78)

This condition preserves the probability content in both the original and the standard normal spaces.

2. The value of the correlation coefficient in the normal space lies between -1 and +1.

For a pair of nonnormal stochastic variables Xj and Xk with known means ц j and nk, standard deviations oj and ok, and correlation coefficient pjk, Eq. (4.77) can be applied to solve for pjjk. To avoid the required computation for solving pjjk in Eq. (4.74), Der Kiureghian and Liu (1985) developed a set of semiempirical formulas as

pjk — Tjkpjk (4.79)

in which Tjk is a transformation factor depending on the marginal distributions and correlation of the two random variables considered. In case both the random variables under consideration are normal, the transformation factor Tjk has a value of 1. Given the marginal distributions and correlation for a pair of random variables, the formulas of Der Kiureghian and Liu (1985) compute the corresponding transformation factor Tjk to obtain the equivalent correlation pjk as if the two random variables were bivariate normal random variables. After all pairs of stochastic variables are treated, the correlation matrix in the correlated normal space Rz is obtained.

Ten different marginal distributions commonly used in reliability computa­tions were considered by Der Kiureghian and Liu (1985) and are tabulated in Table 4.4. For each combination of two distributions, there is a corresponding formula. Therefore, a total of 54 formulas for 10 different distributions were developed, and they are divided into five categories, as shown in Fig. 4.13. The complete forms of these formulas are given in Table 4.5. Owing to the semiem­pirical nature of the equations in Table 4.5, it is a slight possibility that the resulting pjk may violate its valid range when pjk is close to -1 or +1.

Based on the normal transformation of Der Kiureghian and Liu, the AFOSM reliability analysis for problems involving multivariate nonnormal random variables can be conducted as follows:

Step 1: Apply Eq. (4.77) or Table 4.5 to construct the correlation matrix Rz for the equivalent random variables Z in the standardized normal space.

Step 2: Decompose correlation matrix Rz to find its eigenvector matrix Vz and eigenvalues Xz’s using appropriate orthogonal decomposition techniques. Therefore, Z’ — Л-1/2 VzZ is a vector of independent standard normal ran­dom variables.

TABLE 4.4 Definitions of Distributions Used in Fig. 4.13 and Table 4.5

Подпись: Moments and parameters relationsAFOSM reliability analysis for nonnormal correlated stochastic variables
Distributions PDF

Подпись: Distribution of Xk N U | E | T1L T1S L | G | T2L | T3S Distribution of Xj N U E T1L T1S L G T2L T3G Tk CAT-1 Tjk = Const CAT-2 Tjk = fW | CAT-3 Tjk = f(pjk> CAT-4 Tjk = f(Wk, pk> CAT-5 Tjk = f(Wj> Wk> pjk>

Note:

Подпись: T1S = Type 1 smallest L = Lognormal G = Gamma T2L = Type 2 largest T3S = Type 3 smallestN = Normal

U = Uniform

E = Shifted exponential

T1L = Type 1 largest

pk = Correlation coefficient

Figure 4.13 Categories of the normal transformation factor Tjk – (After Der Kiureghi-n and Liu, 1985).

AFOSM reliability analysis for nonnormal correlated stochastic variables

TABLE 4.5 Semiempirical Normal Transformation Formulas (a) Category 1 of the transformation factor j in Fig. 4.13

U

E

R

T1L

T1S

N

Tjk = constant

1.023

1.107

1.014

1.031

1.031

Max. error

0.0%

0.0%

0.0%

0.0%

0.0%

NOTE: Distribution indices are N = normal; U = uniform; E = shifted exponential; R = shifted Rayleigh; T1L = type 1, largest value; T1S = type 1, smallest value.

(b) Подпись: 195
Category 2 of the transformation factor Tjk in Fig. 4.13

L

G

T2L

T3S

Tjk = f (Qk)

N

Max. error

Qk

1.001 – 1.007Qk + 0.118Q 0.0%

1.030 + 0.238Qk + 0.364Q 0.1%

1.031 – 0.195Qk + 0.328Qk 0.1%

Zln(1+Qk)

Exact

NOTE: Qk is the coefficient of variation of the j th variable; distribution indices are N type 3, smallest value.

SOURCE: After Der Kiureghian and Liu (1985).

= normal; L = lognormal; G = gamma; T2L

= type 2, largest value; T3S =

(Continued)

U

E

R

T1L

T1S

U

Tjk = f(Pjk)

1.047 – 0.047pjk

1.133 + 0.029pjk

1.038 – 0.008p2k

1.055 + 0.015p2k

1.055 + 0.015p2k

Max. error

0.0%

0.0%

0.0%

0.0%

0.0%

E

Tjk = f(Pjk)

1.229 – 0.367pjk

1.123 – 0.100pjk

1 . 142 – 0 . 154 p jk

1.142 + 0.154p jk

+ °.153p! k

+ 0.021p|k

+ 0.031p|k

+ °.°31p2k

Max. error

1.5%

0.1%

0.2%

0.2%

R

Tjk = f(Pjk)

1.028 – 0.029pjk

1 . 046 – 0 . 045 p jk

1.046 + 0.045p jk

+ 0.006p2k

+ 0.006p2jk

Max. error

0.0%

0.0%

0.0%

T1L

Tjk = f(Pjk)

1.064 – 0.069pjk

1.064 + 0.069p jk

+ 0.005pj

+ 0.005pjk

Max. error

0.0%

0.0%

T1S

Tjk = f(Pjk)

1.064 – 0.069pjk

+ 0.005p2k

Max. error

0.0%

TABLE 4.5 Semiempirical Normal Transformation Formulas (Continued) (c) Category 3 of the transformation factor Tjk in Fig. 4.11

Подпись: 196
NOTE: pjk is the correlation coefficient between the j th variable and the kth variable; distribution indices are U = uniform; E = shifted exponential; R = shifted Rayleigh; T1L = type 1, largest value; T1S = type 1, smallest value.

L

G

T2L

T3S

U

Tjk — f(pjk, Qk )

1.019 + 0.014Qk + 0.010p2k + 0.249Q2

1.023 – 0.007Qk + 0.002p2k + 0.127Q?

1.033 + 0.305Qk + 0.074p2k

+ 0.405Qk

1.061 – 0.237Qk – 0.005p2jk + 0.379Q?

Max. error

0.7%

0.1% k

2.1% k

0.5% k

E

Tjk — f (pjk, Qk )

1.098 + 0.003pjk + 0.019Qk + 0.025p2k + 0.303Q2 – 0.437pjkQk

1.104 + 0.003pjk – 0.008Qk + 0.014p2k + 0.173Qk – 0.296pjkQk

1.109 – 0.152pjk + 0.361Qk + 0.130p2k + 0.455 Q2 – 0.728pjkQk

1.147 + 0.145pjk – 0.271Qk + 0.010p2k + 0.459Qk – 0.467pjkQk

Max. error

1.6%

0.9%

0.9%

0.4%

R

Tjk — f (pjk, Qk )

1.011 + 0.001pjk + 0.014Qk + 0.004p2k + 0.231Qk – 0.130pjkQk

1.014 + 0.001pjk – 0.007Qk + 0.002p2k + 0.126Qk

– 0.090pjkQk

1.036 – 0.038pjk + 0.266Qk

+ 0.028p2k + 0.383 Qk – 0.229pjkQk

1.047 + 0.042pjk – 0.212Qk + 0.353Qk – 0.136pjkQk

Max. error

0.4%

0.9%

1.2%

0.2%

T1L

Tjk — f (pjk, Qk )

1.029 + 0.001pjk + 0.014Qk + 0.004p2k + 0.233Qk -0.197pjkQk

1.031 + 0.001pjk – 0.007Qk + 0.003p2k + 0.131Qk -0.132pjkQk

1.056 – 0.060pjk + 0.263Qk + 0.020p2k + 0.383 Qk -0.332p jkQk

1.064 + 0.065pjk – 0.210Qk + 0.003p2k + 0.356Qk -0.211pjkQk

Max. error

0.3%

0.3%

1.0%

0.2%

T1S

Tjk — f (pjk, Qk )

1.029 + 0.001pjk + 0.014Qk + 0.004p2k + 0.233Qk + 0.197p jkQk

1.031 – 0.001pjk – 0.007Qk + 0.003p2k + 0.131Qk

+ 0.132pjk Qk

1.056 + 0.060pjk + 0.263Qk + 0.020p2jk + 0.383 Qk

+ °.332pjk Qk

1.064 – 0.065pjk – 0.210Qk + 0.003p2k + 0.356Qk + 0.211p jkQk

Max. error

0.3%

0.3%

1.0%

0.2%

NOTE: pjk is the correlation coefficient between the j th variable and the kth variable; Qk is the coefficient of variation of the kth variable; distribution indices are U = uniform; E = shifted exponential; R = shifted Rayleigh; T1L = type 1, largest value; T1S = type 1, smallest value; L = lognormal; G = gamma; T2L = type 2, largest value; T3S = type 3 smallest value.

Подпись: 197
(Continued)


Подпись: 198

TABLE 4.5 Semiempirical Normal Transformation Formulas (Continued) (e) Category 5 of the transformation factor Tjk in Fig. 4.13

 

L G T2L T3S

 

Tjk — f (pjk, Qk) ——— 1п(1+р-^ ak) 1.001 + 0.033pjk + 0.004Qj

pjky 1n 0+j ln(1+Qk) – 0.016^k + 0.002pjk

+ 0.223Q2 + 0.130^k
– 0.104pjkQj + 0.029Ц; Qk
– 0.119pjk&k

Max. error Exact 4.0%

 

1.026 + 0.082pjk – 0.019Qj
– 0.222Qk + 0.018pjk + 0.288Q2
+ 0.379Q2 – 0.104pjkQj
+ 0.12601 j Qk – 0.277pjkQk

4.3%

 

1.31 + 0.052pjk + 0.011Q j

– 0.21Qk + 0.002p2k + 0.22Q2

+ 0.35Qk + 0.005pQj-
+ 0.009Qj Qk – 0.174pQk

2.4%

1.32 + 0.034pjk – 0.007Qj – 0.202Qk + 0.121Q2

+ 0.339Q2 – 0.006pQj
+ 0.003Q7^ Qk – 0.111pQk

4.0%

1.065 + 0.146pjk + 0.241Q j

– 0.259Qk + 0.013p2k + 0.372Q2

+ 0.435Q2 + 0.005pQj-
+ 0.034Qj Qk – 0.481pQk

 

L

 

AFOSM reliability analysis for nonnormal correlated stochastic variables

3.8%

 

1.063 – 0.004pjk – 0.200(Qj + Qk)
– 0.001pj + 0.337(Q2 + Qk)

+ 0.007p(Qj + Qk) – 0.007Qj Qk
2.62%

 

T3S Tjk — f (pjk ,Qj, Qk)

 

Max. error

 

NOTE: pjk is the correlation coefficient between the jth variable and the kth variable; Qj is the coefficient of variation of the j th variable; Qk is the coefficient of variation of the kth variable; distribution indices are L — lognormal; G — gamma; T2L — type 2, largest value; T3S — type 3, smallest value.

 

Step 3: Select an initial point x(r) in the original parameter space X, and com­pute the sensitivity vector for the performance function sx,(r) = VxW(x(r>).

AFOSM reliability analysis for nonnormal correlated stochastic variables Подпись: (4.80)

Step 4: At the selected point x(r), compute the means (j, N,(r) = (p.1N, p.2N,…, IJ-knY and standard deviations aN,(r) = (o1N, o2N,…, oKN)1 of the normal equivalent using Eqs. (4.59) and (4.60) for the nonnormal stochastic variables. Compute the corresponding point zr) in the independent standardized nor­mal space as

in which Dx, N,(r) = diag(o2N, o^N,…, oKN), a diagonal matrix containing the variance of normal equivalent at the selected point x(r). The correspond­ing reliability index can be computed as fi(r) = sign[W/(0)]|z(r)|.

Step 5: Compute the vector of sensitivity coefficients for the performance function in Z’-space sz>,(r) = Vz> W(zr)), by Eq. (4.68), with Dx replaced by D x, n,(r), and x and &x replaced by V’z and Л^, respectively. Then the vector of directional derivatives in the independent standard normal space az ,(r) can be computed by Eq. (4.67).

Step 6: Apply Eq. (4.51) of the Hasofer-Lind algorithm or Eq. (4.70) of the Ang-Tang algorithm to obtain a new solution z (r +1).

Step 7: Convert the new solution z(r+1) back to the original parameter space by Eq. (4.66a), and check for convergence. If the new solution does not satisfy convergence criteria, go to step 3; otherwise, go to step 8.

Step 8: Compute the reliability, failure probability, and their sensitivity vec­tors with respect to change in stochastic variables.

Note that the previously described normal transformation of Der Kiureghian and Liu (1985) preserves only the marginal distributions and the second-order correlation structure of the correlated random variables, which are partial statistical features of the complete information represented by the joint dis­tribution function. Regardless of its approximate nature, the normal transfor­mation of Der Kiureghian and Liu, in most practical engineering problems, rep­resents the best approach to treat the available statistical information about the correlated random variables. This is so because, in reality, the choices of multivariate distribution functions for correlated random variables are few as compared with univariate distribution functions. Furthermore, the derivation of a reasonable joint probability distribution for a mixture of correlated non­normal random variables is difficult, if not impossible. When the joint PDF for the correlated nonnormal random variables is available, a practical normal transformation proposed by Rosenblatt (1952) can be viewed as the generaliza­tion of the normal transformation described in Sec. 4.5.5 for the case involving independent variables. Notice that the correlations among each pair of ran­dom variables are implicitly embedded in the joint PDF, and determination of correlation coefficients can be made according to Eqs. (2.47) and (2.48).

The Rosenblatt method transforms the correlated nonnormal random vari­ables X to independent standard normal random variables Z’ in a manner similar to Eq. (4.78) as

z[ = Ф ЧFi(xi)] z2 = Ф-1[F2(X2 |xi)]

Подпись: (4.8i)zk = Ф 1[Fk(Xk|xi, X2, Xk-i)]

z’K = Ф 1[Fk(XK|Xi, X2,Xk—1)]

Подпись: f(Xi,X2, •••,Xk—i,Xk) f (Xi, X2, ..., Xk — i)
Подпись: fk (Xk |Xi, X2,..., Xk—i)

in which Fk(Xk |Xi, X2,, Xk—i) = P(Xk < Xk |x1, X2,…, Xk—i) is the conditional CDF for the random variable Xk conditional on X1 = X1, X 2 = X2,…, Xk—1 = Xk—1. Based on Eq. (2.17), the conditional PDF fk (Xk X2,…, Xk—1) for the random variable Xk can be obtained as

Подпись: Fk (Xk |xi, X2,..., Xk—i) Подпись: /—^ f (Xi, X2, ..., Xk — i, t) dt f (Xi, X2, ..., Xk — i) Подпись: (4.82)

with f (x1,X2,…,Xk—1,Xk) being the marginal PDF for X1,X2,…,Xk—1,Xk; the conditional CDF Fk(xk |x1, x2,…, xk—1) then can be computed by

To incorporate the Rosenblatt normal transformation in the AFOSM algo­rithms described in Sec. 4.5.5, the marginal PDFs fk (xk) and the conditional CDFs Fk(xk|x1, x2,…, xk—1), for k = 1, 2,…, K, first must be derived. Then Eq. (4.81) can be implemented in a straightforward manner in each itera­tion, within which the elements of the trial solution point x(r) are selected successively to compute the corresponding point in the equivalent independent standard normal space z(rand the means and variances by Eqs. (4.80) and (4.81), respectively. It should be pointed out that the order of selection of the stochastic basic variables in Eq. (4.81) can be arbitrary. Madsen et al. (1986, pp. 78-80) show that the order of selection may affect the calculated failure probability, and their numerical example does not show a significant difference in resulting failure probabilities.

STEP 7 SHEATHE THE ROOF

Sheathing a roof is much like sheathing a floor, except that the deck is sloped, not flat, and you work at least 10 ft. off the ground. Anyone who has worked in the construction trades for more than a few years has heard stories about someone who has fallen from a roof—or has seen it happen. I was sheath­ing a roof many years ago on a cool morning with a bit of frost on the ground. The sunny side of the roof had no frost. Without think­ing, I stepped onto the shady side of the roof and was immediately careening down a fairly steep pitch, heading for doom. Fortunately, I had my straight-clawed hammer in my hand. Instinctively using it like an ice ax, I sunk the claw into the sheathing, stopping myself just short of the roof’s edge—a thrilling way to drive up my heart rate at the beginning of the day but not an experience I’d care to repeat. Take care, and stay aware.

MAKING A PLATFORM FOR ROOF SHEATHING

STEP 7 SHEATHE THE ROOFA safe strategy for hoisting sheathing onto a roof is to build a simple stag­ing platform, as shown in the photo at right. Nail the platform’s two hori­zontal supports (a pair of 2x4s works fine) to the wall framing or, if the wall has been sheathed already, to a 2x cleat nailed through the sheathing and into the studs. The supports must be a couple of feet above the bottom plate of the wall. Space them about 32 in. apart, and make them roughly level. Support the outboard end of the platform with 2x legs firmly attached to the horizontal supports. Nail a 2x on top of the platform near the outer end to provide additional stability. If necessary, install diagonal braces between the supports and the legs or the wall framing for added strength. Then set 4×8 sheets of plywood or OSB on edge on the platform; workers on the roof can grab the sheets as needed.

Подпись: Sheathing work begins. Position the first row of sheathing with the top edge against a snapped reference line.

Measure 481/4 in. from the outside edge of the gutter or fascia board at each end of the roof and snap a chalkline. Lay the first row of plywood or OSB so that the top edge is right on this line (see the photo at left). Make sure the sheathing extends past the gable-end truss all the way to the barge rafter, which the sheath­ing helps support. Lay the slick side of the OSB down. Nail the sheets with 8d nails at 6 in. o. c. at the edges and 12 in. o. c. in the field. Be sure to nail all the boards.

Before you start the second row of sheath­ing, put plywood H-clips, centered between the rafter chords, on the first row (see the top photo on the facing page). Required on /’2-in. sheath­ing (but not on 5/8-in. sheathing), these clips hold two sheets together and make the roof’s surface stronger. Start the second row at one end with a 4-ft.-sq. sheet so that the courses will be stag­gered, just as they are with floor sheathing. Continue sheathing until you reach the top. If a ridge vent will be installed, leave a gap at the ridge so that air inside the attic can move up into the vent. If the vent is available, read the

Подпись: Using H-clips between rafters. Required on 1/2-in. roof sheathing, H-clips increase the rigidity of the roof by locking together panel edges between framing members. Подпись: An air-operated nailgun can be used to fasten tarpaper securely to the roof before shingles are laid in place. [Photo by Don Charles Blom]

Подпись: Stay cool. Roofing can be hot work. Be sure to drink plenty of water, take breaks, and go down if you begin to feel weak. Remind others to do the same.

manufacturer’s instructions regarding the size of the gap and check with your building inspec­tor regarding these construction details. The gap need not run all the way to the barge rafter. Start it about 1 ft. in on the main roof.

Patching Foundation Cracks

Determine the cause of the crack and fix that first; otherwise the crack may recur. Shallow foundation cracks less than % in. wide are usually caused by normal shrinkage and needn’t be patched, unless their appearance disturbs you or they leak water. However, you should repair any cracks that go all the way through the foundation: Probe with a thin wire to see if they do.

Of the many crack-repair materials, there are three main types: cement-based, epoxy, and polyurethane foams. When working with any of these materials, wear dis­posable rubber gloves, eye protection, and a respirator mask with changeable filters.

Cement-based materials such as hydraulic cement are mixed with water and troweled into cracks. To ensure a good connection, first use a masonry chisel and hand sledge to enlarge the crack; angle the chisel to undercut the crack, making it wider at the back, like a rabbet joint in woodworking. Then wire-brush the crack to remove debris. Next, dampen the surfaces, fill the crack with hydraulic cement, and feather out the edges so the repaired area is flat. Work fast because most hydraulic cement sets in 10 minutes to 15 minutes and expands so quickly that it can stop the flowing water of an active leak.

Epoxies range from troweled-on pastes to injection systems that pump epoxy deep into cracks. Application details vary, but many injection systems feature surface ports, which are plastic nozzles inserted into the crack along its length. You should space ports 8 in. apart before temporarily capping them. Then seal the wall surface with epoxy gel or hydraulic cement, which acts as a dam for the epoxy liquid you’ll inject deep into the wall through the ports. Working from the bottom, uncap each surface port, insert the nozzle of the applicator, and inject epoxy till it’s visible in the port above. Cap the port just filled, and then move up the wall, port by port.

Epoxy is famously strong. The manufacturer of Simpson Crack – Pac™ claims that its injected epoxy achieves 11,000 psi com­pressive strength when cured for 7 days. (Foundation concrete averages 3,000 psi to 4,500 psi.)

Consequently, injected epoxy, which bonds to both sides of the crack, is a true structural repair, not just a crack filler. There are a couple of disadvantages: cost and curing time. Epoxy takes hours to harden, so it can ooze out the back of the crack, if there’s a void between the soil and the founda­tion wall—as there often is. If your main concern is water leaks and not structural repairs, polyurethane foam is probably a better choice.

Polyurethane foam is applied in many ways, including the surface-port injection just described for epoxies. Polyurethane sets up in minutes, so it’s unlikely to sag or run out the back of the crack. It’s largely unaffected by water, so you can inject it into a damp crack. Unlike epoxy or cement-based fillers, polyurethane is elastomeric (meaning it stays flexible), so it’s great for filling foundation cracks that expand and contract seasonally. One disadvantage is that it has little compressive strength and hence does not create a structural repair.

Подпись:

beams, stick with wood posts: Fir 6x6s are less likely to migrate than steel columns.

Cribbing. Cribbing refers to a framework of usually squared timber (often 6x6s) stacked perpendicular in alternate layers to create a sta­ble platform for jacking or shoring house loads. In earthquake country, foundation contractors "shear wall” cribbing higher than 8 ft.—that is, they temporarily nail h-in. plywood to the crib­bing, using duplex nails. The precaution is worth the trouble: in 1989 a California house resting on 13-ft.-high shear-walled cribbing remained standing through a 7.1 quake.

Braces and connectors. To keep posts plumb and prevent structural elements from shifting, builders use a variety of braces and connectors such as these:

► Diagonal 2×4 braces 3 ft. or 4 ft. long are usually nailed up with double-headed nails for easy removal.

► Plywood gussets are acceptable if space is limited.

► Metal connectors such as Simpson hurricane ties, post caps, and post-to-beam

connectors are widely used because they are strong and quick to install.

Jacks. House-raising screw jacks and hydraulic jacks are by far the most common types. For safety, all jacks must be placed on a stable jack­ing platform and plumbed.

Screw jacks vary from 12 in. to 20 in. (closed height), and extend another 9 in. to 15 in. Never raise the threaded shaft more than three-quarters
its total length because it would be unstable beyond that. Screw jacks are extremely stable: Of all types, they are the least likely to fail or lower unexpectedly under load. But they require a lot of muscle and at least 2 ft. of space around the jack for operation.

Hydraulic jacks are the workhorses of founda­tion repair and are rated according to the loads they can bear, such as 12 tons. In general, hydraulic jacks are easier to operate than screw jacks, and they fit into tighter spaces. They are lowered by turning a release valve and so can’t be lowered incrementally. Because hydraulics release all at once, many house movers use hydraulics to raise a house and screw jacks to lower it gradually.

Because the head of a hydraulic jack is rela­tively small, you need to place a 4-in. by 4-in. by f4-in. steel plate between it and the wood it sup­ports so the head doesn’t sink in during jacking. Safety note: Before lowering the jack, have a helper remove the steel plate as pressure is released. Otherwise, the plate could fall and injure the jack operator. Alternatively, have the plate predrilled so you can screw or nail it to the underside of the beam.

image423

Unsafe! Although post jacks such as this are widely used as temporary shoring, they are not strong enough for house loads. Here footing blocks are also undersize, and the post is badly out of plumb.

Unsuitable for raising a house. Postjacks employ a screw mechanism but are of flimsier construction than the compact screw jack described in the previous section. They tend to be fashioned from lightweight steel, with slender screws that could easily distort when loaded beyond their capacity. So use post jacks only for low-load, very temporary situations.

European Legislation

Across Europe, the legislation on the influence of road and road traffic on water and water bodies and associated ecosystems is wide and complex. European legislation in general prohibits water pollution and limits influences on the water biotopes. These general rules are transferred into national legislation in very different ways. Realization of these rules depends on the country’s prevailing natural conditions (e. g. climatic regime), uses of water and technical regulations concerning road plan­ning, design, construction and maintenance. In general, water pollution from roads is regulated in two main groups of legislation: environmental law and construction law. This section refers to environmental law.

Water is one of the most comprehensively regulated areas of the EU environmen­tal legislation with directives regulating quality and standards for, e. g., dangerous substances in water, fishing water, drinking water and groundwater. The Water Framework Directive (WFD) of 2000 (EU, 2000) is the most important directive under the group of environmental law that regulates water pollution. The Ground­water Directive (EU, 2006), on the protection of groundwater against pollution and deterioration, is also a feature of the WFD.

The purpose of the WFD is to establish a framework for the protection of inland surface waters, transitional waters, coastal waters as well as groundwater. It aims at enhanced protection and improvement of the aquatic environment, and ensures the progressive reduction of pollution of water, based on a long-term protection and prevention of further pollution. Common environmental quality standards and emission limit values for certain groups or families of pollutants should be laid down as minimum requirements in Community legislation.

At latest 15 years after the date of entry into force of the WFD, i. e. 2015, Member States shall have protected all their water bodies with the aim of having a good water status. Good water quality is such that the concentrations of pollutants do not exceed the quality standards applicable under other relevant Community legislations.

Furthermore, the WFD presents an indicative list of what in general is considered the main groups of pollutants in water. Some of these are toxic while others are nutrient salts or substances causing oxygen depletion. In particular a number of priority substances have been listed and given special attention (the List of Priority Substances in the field of water policy). The List contains 33 substances [http:// europa. eu. int/comm/environment/water/water-framework/priority _substances. htm]. Some of these are typical traffic and road pollutants.

The substances on the list are already controlled, to varying degrees, by EU and national legislation. Further controls, independent of the WFD, are expected for a number of substances as a result of European and other international regulations. The European Parliament and the European Council will adopt specific measures against pollution of water by individual pollutants or groups of pollutants presenting a significant risk to or via the aquatic environment, including such risks to waters used for the abstraction of drinking water. For those pollutants, measures will be aimed at the progressive reduction and, for priority hazardous substances, at the cessation or phasing out of discharges, emissions and losses.