Fat Spots of Mastic with Segregation

An area with a definite shortage of mastic adjacent to the fat spot (visibly porous) is a clear sign that this is a case of an SMA segregation—namely, separating the coarse aggregates from the mastic. If the quantities of all the ingredients have been properly selected, the high accumulation of one component in one location will result in a reduced quantity of that component in another. When an excess of mastic (fat spot) appears somewhere, the coarse aggregate content rises elsewhere, so the total sum of the components remains constant. Figure 11.2 presents a classic fat spot in a segre­gated SMA mixture. Figure 11.3 shows the difference between fat spot and adjacent porous section and a close-up of the mastic-rich area.

It is worth emphasizing that such segregation may happen for one or more of the following reasons:

• Substandard production of an SMA mixture

• Lack of a stabilizer, its improper metering, or its poor quality

• Excessive production temperature

• Too short a time of mixing components

• Too long a storage time of a mixture in an asphalt plant storage silo

• Improper laydown of SMA (with an improper setup of a paver)

image110

figure 11.2 SMA mixture segregation—separation of mastic from coarse aggregates. (Photo courtesy of Krzysztof Blazejowski.)

STEP 3 Install the Foundation and Floor Framing

Concrete piers and FT posts work well for supporting the front of the porch. In some areas, code may require that concrete porch piers be set on concrete footings, so check with your building department. For a deck that’s 6 ft. wide by 16 ft. long, set three piers (16 in. square by 12 in. deep), one on each corner and one in the middle (see the top illustration at right). Shorter decks can be built with a concrete pier on each corner; longer decks need more piers. I like to use precast piers that have steel post anchors set in them. The anchors hold the posts in place and resist wind uplift. Check your house plans for porch width and set the piers so they are inline with the ledger board and square with the building.

Next, measure the length for the posts that will extend from the piers to support the floor framing. You can do this with a 6-ft. level or with a shorter level attached to a straightedge (see the bottom illustration at right). Lay the rim joist (or a scrap board of the same size) on top of each pier and set the level or straightedge on the ledger, extending it directly out over the pier. The distance between the rim joist on the pier and the level or straightedge is the post’s length. Cut those posts from PT 4x4s; make them Vi in. short (be consistent) so that the deck will slope away from the house just a bit.

Cut the two end beams (girders) first, using PT 4×6 lumber or doubled 2x6s, as shown in the top illustration at right. For a deck that is 6 ft. wide, cut the two end beams at 5 ft. 8 in. The ledger and rim joist will add 3 in. to the overall width. Those beams connect to the ledger by a metal framing connector and rest, with 2 in. bearing, on the end posts. Connect any beams falling between in the same man­ner, but run them long over the tops of their

STEP 3 Install the Foundation and Floor Framing

Подпись: THE CORNER POST IS CRUCIAL. Holding a long level against the flat sections of a turned post, a volunteer makes sure the post is plumb.Подпись: іПодпись: Helping HandПодпись: Install joist hangers with special nails. Joist hangers and other steel framing hardware should be installed with the special hanger nails sold with them. Common framing nails have thinner shanks, so they're not as strong. When you buy hanger nails, make sure they have a rust-resistant coating.posts. Stretch a chalkline from the ends of the two end beams across the interior beams and snap a line. Cutting the interior beams to length in this manner ensures a straight rim joist in the front.

Next, cut the rim joist to length. On a rect­angular deck, the rim joist is the same length as the ledger. If you have a long deck and use several pieces of rim, make sure they break over a post. The rim rests on the posts and is nailed into each beam with two 16d galva­nized nails. Toenail both the beam and the rim to the post. Then reinforce the beam – post-rim joist connections with metal framing connectors. You can nail a flat, gusset-type connector over the joint between a post and the rim joist and use right-angled connectors on the inside.

Before installing the joists between beams, make sure the post-and-beam assembly is par­allel and square with the house and all the posts are plumb. Brace the porch frame so it

will remain square until the stairs are attached and the decking is screwed in place. When cutting and installing joists, I recommend using joist hangers to ensure that all joist-to – beam connections are strong. The joist spac­ing you use depends on the decking material you plan to install. A 24-in. o. c. spacing is usu­ally adequate for 1 А-in.-thick PT decking boards. For 5/4 (lM-in.-thick) PT decking, use

16- in. o. c. spacing. If you use any of the syn­thetic decking material that’s becoming more popular these days, follow the manufacturer’s recommendations for joist spacing.

STEP4 Frame the Stairs

I taught night school at a community college for 20 or so years. My students were appren­tice carpenters learning how to build houses. Often, students were hesitant to take on the task of building stairs because of the pre­sumed difficulty. It came as a surprise to most of them that building stairs—especially a simple, straight flight of stairs—is actually quite easy. If you can do some basic math and know how to use a framing square and a circular saw, you can build stairs. Although stair-building principles are the same every­where, different states (and towns or cities) sometimes use different codes, so check to see which code requirements apply in vour area.

Figure out the risers

The accepted standards for a typical stairway call for a rise of about 7 in. and a run, or tread width, of 11 in. When calculating the number of risers in a stairway, aim to stay as close as possible to those figures. If you have a pocket calculator handy, this calculation is easy to do.

First, determine exactly how high each riser will be. This is calculated based on the total rise, which is measured from finish floor to

STEP 3 Install the Foundation and Floor Framing

MEPDG

The above methods define stiffness as a function of stress alone. Full incorporation of the effects of moisture (as a pressure or suction) should necessitate use of an effective stress framework (see Section 9.5). However a more simple approach, at least in principle, is to adjust the stiffness value calculated by one of the above rela­tionships using a factor that is dependent on the moisture (and, perhaps, other) con­dition. The AASHTO ‘Mechanistic-Empirical Pavement Design Guide’ (MEPDG) takes this approach, though it’s attention to many details makes the implementation rather complex (ARA, 2004). In this approach, the reference stiffness value, Mropt (the value of Mr at optimum conditions), is adjusted by a factor, Fenv, to allow for different environmental effects, with the value of each factor being computed for each of a range of depths, lateral positions and time increments. For moisture the adjustment factor is based on the equation

Mr

Mr oP^ min

Where km is a material parameter and Sr and Sropt = the actual saturation and the saturation ratio at optimum conditions, respectively. The actual saturation value is obtained from the use of the Soil Water Characteristic Curve (SWCC) see Chapter 2, Section 2.7.1. Other adjustments are included in the Fenv factor to allow for freez­ing, thawing and temperature. The full approach is too detailed to include here. Interested readers are directed to the relevant report (ARA, 2004).

Long et al. (2006) take another approach, relating modulus to suction and water content rather than to saturation ratio, but still including some stress influence:

(p – 0 ■ 5) + ^t34^ (1 + V)(1 – 2v)

Yh(0.435) (1 – v)

where p is the mean normal stress on the element of soil, 0 and w are the volumetric and gravimetric water contents, respectively, 5 is the matric suction pressure, S0 is the slope of the soil desorptive curve (the rate of change of the logarithm of 5 with the logarithm of 0), Yh is the suction volumetric change index (an indicator of the sensitivity of volume change to change in matric suction) and v is Poisson’s ratio.

Drilling and Notching Studs and Joists

Подпись: Notching and Drilling LimitsПодпись: JOISTS

It’s often necessary to notch or drill framing to run supply and waste pipes.

If you comply with code guidelines, given in "Maximum Sizes for Holes and Notches," on p. 287, you’ll avoid weakening the struc­ture. Although that table is based on the following rules of thumb, remember that local building codes have the final say.

Joists

You may drill holes along the entire span of a joist, provided the holes are at least 2 in. from the joist’s edge and don’t exceed one – third of the joist’s depth. Notches are not
allowed in the middle third of a joist span. Otherwise, notches are allowed if they don’t exceed one-sixth of the joist’s depth.

Studs

Drilled holes must be at least 78 in. from the stud’s edge. Ideally, holes should be centered in the stud. If it’s necessary to drill two holes in close proximity, align the holes vertically, rather than drilling them side by side. Individual hole diameters must not exceed 40 percent of the width of a bearing-wall stud, if those studs are doubled and holes don’t pass through more than two adjacent
doubled studs; hole diameters must not exceed 60 percent of the width of non­bearing-wall studs. Notch width may not exceed 25 percent of the width of a bearing – wall stud or 40 percent of the width of a nonbearing-wall stud.

Edge protection

Any pipe or electrical cable less than 11/ in. from a stud edge must be protected by steel nail plates or shoes at least Ум in. thick, to prevent puncture by drywall nails or screws.

Pipe Slope

DWV pipes slope, so before drilling or notch­ing framing, snap sloping chalklines across the stud edges; then angle your drill bits slightly to match that slope. Drill holes 74 in. larger than the outside dimension of the pipe, so the pipe feeds through easily. Nonetheless, if DWV pipe runs are lengthy, you may need to cut pipe into 30-in. sections (slightly shorter than the distance between two 16-in. on-center studs) and join pipe sections with couplings. That is, it may be impossible to feed a single uncut DWV pipe through holes cut in a stud wall.

image593Подпись: STUDS When hole diameters exceed maximur allowed by code, reinforce framing wi1 a steel stud shoe.

_

tim: –

W

The toilet flange (orange ring) will sit atop the finish floor. So if the finish floor is not yet installed, place scrap under the flange, elevating it to the correct height. This assembly is essentially the same as that shown in “Constricted Spaces," on p. 282.

 

Support vent stacks in mid-story by using plumber’s strap to tie stacks to blocking between studs.

 

image595

Подпись: TIPПодпись: Use only noncorroding (brass or stainless-steel) screws and bolts to secure the closet flange or the toilet bowl; other materials will corrode. To help you align the bolt holes on the bowl with bolts in the closet flange, buy extra-long, 3-in. by 5/i6-in. closet bolts. They'll be long enough to line up easily, even when the wax ring is in the way, and you can trim excess length without difficulty. 1111

Once you’ve secured the closet bend, add pipe sections to the bottom of the bend, back to the takeoff fitting on the main drain that you installed earlier. Maintain a minimum of!4 in. per foot slope, and support drains at least every 4 ft. Dry-fit all pieces, and use a grease pencil to make alignment marks on pipes and fittings.

Other fixture drains. Next run the 1!4-in., 112-in., and 2-in. fixture drains up from the main drain takeoff. Drains must slope at least 14 in. per foot, and all pipe must be rigidly supported every 4 ft. and at each horizontal branch connection. Support pipes with rigid plastic pipe hangers or with plastic-pipe strap, securing pipes to wood blocks beneath them. Support stacks at the base, and in mid-story by strapping or clamping the pipe to a 2x block running between studs.

Run the tub branch drain to the subfloor opening where the tub trap arm will descend.

Pipe stub-outs for lavs and sinks should stick out into living spaces 6 in. or so; you can cut them off or attach trap adapters later. All branch drains end in a sanitary tee. The horizontal leg of the tee receives the trap arm from the fixture, and the upper leg of the tee is the beginning of the branch vent.

Vent runs. Next assemble vent runs, starting with the largest vent—often the 2-in. or 3-in. pipe rising from the combo fitting below the closet bend. Individual branch vents then run to that vent stack, usually joining it in an inverted tee fit­ting, typically 4 ft. to 5 ft. above the floor. Support all stacks in mid-story with clamps or straps. Horizontal runs of 112-in. branch vents must be at least 42 in. above the floor, or 6 in. above the flood rim of the highest fixture, and those runs typically slope upward at least 14 in. per foot. Continue to build up the vent stack, with as few jogs as possible, until it eventually passes through a flashing unit set in the roof. For code requirements at the roof, see "Vent Termination,” on p. 284.

EXAMPLES FROM THE DEMONSTRATION PROJECTS

Подпись: Boise, IdahoEXAMPLES FROM THE DEMONSTRATION PROJECTSПодпись: Lincoln, NebraskaTypical Boise streets have sidewalks on both sides. At Lakewood Meadows, the city permitted elimination of sidewalks on one side of the sub­division’s streets and around T – turnarounds. One higher-order collector street was required to have sidewalks on both sides, but a sidewalk on one side only was allowed for a high-volume arterial street. Walkways were provided in common areas and between T – turnarounds.

The builder estimated that 2,696 additional linear feet of sidewalk would have been required to comply with existing Boise standards. Construction costs were decreased by $8,088, a per-unit reduction of $216.

Existing Lincoln standards call for 4- foot wide sidewalks on both sides of all residential streets. At Parkside Village, the city permitted Empire Homes to install З-foot wide sidewalks on one side of the street only. Cost savings were $4,289, or $191 per unit.

County standards call for sidewalks on both sides of residential streets. At the Hermitage Hill affordable housing project, this requirement was waived altogether, and no sidewalks were installed. Savings were $40,348, or $558 for each of the 73 units.

Подпись: Christian County, KentuckyПодпись: Crittenden County, ArkansasRex Rogers, in Harvard Yard, used an 8-foot concrete swale on one side of the street and graded the street so stormwater was channeled to that side. The swale is only slightly angled and doubles as a sidewalk.

Other demonstration sites which eliminated sidewalks altogether or used them on only one side, contrary to normal local practice, include:

Charlotte, North Carolina; Phoenix, Arizona; Tulsa, Oklahoma; Santa Fe, New Mexico; Lacey, Washington; and White Marsh, Maryland.

Pedestrian pathways or meandering walkway systems are used in Phoenix, Arizona and Portland, Oregon.

Generating multivariate random variates subject to linear constraints

Procedures described in Sec. 6.5.2 are for generating multivariate normal (Gaussian) random variables without imposing constraints or restriction on the values of variates. The procedures under this category are also called uncon­ditional (or nonconditional) simulation (Borgman and Faucette, 1993; Chiles and Delfiner, 1999). In hydrosystems modeling, random variables often exist for which, in addition to their statistical correlation, they are physically related in certain functional forms. In particular, this section describes the procedures for generating multivariate Gaussian random variates that must satisfy pre­scribed linear relationships. An example is the use of unit hydrograph model for estimating design runoff based on a design rainfall excess hyetograph. The unit hydrograph is applied as follows:

Pu= q (6.38)

where P is an n x J Toeplitz matrix defining the design effective rainfall hyeto­graph, u is a J x 1 column vector of unit hydrograph ordinates, and q is the n x 1 column vector of direct runoff hydrograph ordinates. In the process of deriving a unit hydrograph for a watershed, there exist various uncertainties rendering u uncertain. Hence the design runoff hydrograph q obtained from Eq. (6.38) is subject to uncertainty. Therefore, to generate a plausible direct runoff hydrograph for a design rainfall excess hyetograph, one could generate unit hydrographs that must consider the following physical constraint:

J

Y^Uj = c (6.39)

j=1

in which c is a constant to ensure that the volume of unit the hydrograph is one unit of effective rainfall.

The linearly constrained Monte Carlo simulation can be conducted by using the acceptance-rejection method first proposed by von Neumann (1951). The AR method generally requires a large number of simulations to satisfy

the constraint and, therefore, is not computationally efficient. Borgman and Faucettee (1993) developed a practical method to convert a Gaussian linearly constrained simulation into a Gaussian conditional simulation that can be im­plemented straightforwardly. The following discussions will concentrate on the method of Borgman and Faucette (1993).

Подпись: Xi
Generating multivariate random variates subject to linear constraints
Подпись: X2* = X2 + CX,12Cx,111(X1* - X1) (6.41) Consider a problem involving K correlated random variables the values X = x of which are subject to the following linear constraints:

Conditional simulation (CS) was developed in the field of geostatistics for modeling spatial uncertainty to generate a plausible random field that honors the actual observational values at the sample points (Chiles and Delfiner, 1999). In other words, conditional simulation yields special subsets of realizations from an unconditional simulation in that the generated random variates match with the observations at the sample points. For the multivariate normal case, the Gaussian conditional simulation is to simulate a normal random vector X2 con­ditional on the normal random vector X1 = x1*. To implement the conditional simulation, define a new random vector X encompassing of Xi and X2 as

generated conditioned on y1 = b. Hence, using the spectral decomposition de­scribed in Sec. 6.5.2.2, random vector X subject to linear constraints Eq. (6.42) can be obtained in the following two steps:

1. Calculate (m + K)-dimensional multivariate normal random vector y by un­conditional simulation as

У = (yO = VyA-°y5 Z + Ъ (6.45)

where y1 is an m x 1 column vector, y2 is a K x 1 column vector; Vy is an (m + K) x (m + K) eigenvector matrix of Cy, and Лу is a diagonal matrix of eigenvalues of Cy, and Z’ is an (m + K) column vector of independent standard normal variates.

2. Calculate the linearly constrained K-dimensional vector of random variates x, according to Eq. (6.41), as

x = y2* = y2 + C y,12C-,n(b – y1) (6.46)

This constrained multivariate normal simulation has been applied, by con­sidering the uncertainties in the unit hydrograph and geomorphologic instan­taneous unit hydrograph, to reliability analysis of hydrosystems engineering infrastructures (Zhao et al., 1997a, 1997b; Wang and Tung, 2005).

Framing for Toilets and Tubs

You may need to cut through joists to accom­modate the standard 4 by 3 closet bend beneath a toilet or the drain assembly under a standard tub. In that event, reinforce both ends of sev­ered joists with doubled headers attached with double-joist hangers. This beefed-up framing provides a solid base for the toilet as well.

If joists are exposed, you can also add joists or blocking to optimize support.

Toilets

A minimum 6-in. by 6-in. opening provides enough room to install a no-hub closet bend made of cast iron (41/2 in. outer diameter) or plastic (З1/? in. outer diameter). The center of the toilet drain should be 12 in. from a finish wall or 1232 in. from rough framing. If joists are exposed, add blocking between the joists to stiffen the floor and better support the toilet bowl, even if you don’t need to cut joists to position the bend.

Bathtubs

A 12-in. by 12-in. opening in the subfloor will give you enough room to install the tub’s waste and overflow assembly. Ideally, there should be blocking or a header close to the tub’s drain, that you can pipe-strap it to. To support the fittings that attach to the shower arm and spout stub-outs, add cross-braces between the studs in the end wall. To support tub lips on three sides, attach ledgers to the studs, using galvanized screws or nails. Finally, if there’s access under the tub, add double joists beneath the tub foot.

a sleeve onto each end of the combo. Align the combo takeoff so it is the correct angle to receive the fixture drain you’re adding. Finally, tighten the stainless-steel clamps onto the couplings.

CONNECTING

BRANCH DRAINS AND VENTS

After modifying the framing, assemble branch drains and vents. Here we’ll assume that the new DWV fittings are plastic.

The toilet drain. After framing the tub drain opening, install the 4 by 3 closet bend, centered 12 in. from the finished wall behind the toilet. Install a piece of 2×4 blocking under the closet bend, and end-nailed through the joists on both ends. Use plastic plumber’s tape to secure the bend to the 2×4. What really anchors the closet bend, however, is the closet flange, which is cemented to the closet bend and screwed to the subfloor.

The flange screws to the subfloor yet will sit atop the finish floor when it’s installed. If the fin­ish floor is not in yet, place scrap under the flange so it will be at the correct height. If, on the other hand, the flange is below the finish floor, you can build up the flange by stacking plastic flange extenders till the assembly is level with the floor. Caulk each extender with silicone as you stack it and use long closet bolts to resecure the toilet bowl. (Check with local codes first, because not all allow extenders.)

CLEARANCES RELATED TO WATER CLOSETS

Подпись:Let’s talk about clearances related to water closets. There’s not a lot to go over, so this can move along quickly. Remember that we are talking about standard plumbing fixtures here, not handicap fixtures. The minimum distance required from the cen­ter of a toilet drain to any obstruction on either side is 15 inches. Measuring from the front edge of a toilet to the nearest obstruction must prove a mini­mum of 18 inches of clear space. When toilets are installed in privacy stalls, you must make sure that the compartments are at least 30 inches wide and at least 60 inches deep. That’s all there is to a typical toilet layout (Fig. 10.7).

URINALS

urinals must have a minimum distance of 15 inches from the center of the drain to the nearest obstruction on either side. If multiple urinals are mounted side by side, there must be a minimum of 30 inches between the two urinal drains. The required clearance in front of a urinal is 18 inches.

LAVATORIES

Подпись:CLEARANCES RELATED TO WATER CLOSETSПодпись: A pedestal lavatory can be a good option if you have limited space to work with. Many pedestal lavatories are available in sizes that are small enough to give you the extra inch, or two, that you may need.Lavatories are not affected by side meas­urements, unless other types of plumbing fixtures are involved. The minimum dis­tance in front of a lavatory should not be less than 18 inches. Obviously, minimum requirements are just that, minimums. It is best when more space can be dedicated to a bathroom in order to make the fix­tures more user-friendly.

Sign-Support Selection

The only types of sign-support systems that should be used are those that have been approved for use by the FHWA. The following concerns should be addressed in the selection of an appropriate single-sign-support system:

• The specifications for support size provided by many states provide information on the maximum sign panel area to be mounted on the support. The shape of the sign as well as the area should be considered when determining the type and number of supports required. For example, a 5-ft X 2-ft (1525-mm X 610-mm) guide sign will have less area than a 4-ft X 4-ft (1220-mm X 1220-mm) warning sign. The wide dimension of the guide sign, however, will result in excessive vibration from wind loads if it is placed on a single sign support without bracing. As a general rule, signs over 40 in (1000 mm) wide should be placed on multiple supports.

• Sign-support systems that are not placed in concrete foundations perform better in strong soils than in weak soils, such as sand. When the system is directly placed in weak soils, an anchor plate, a proper concrete footing, or embedment to a greater depth than used for strong soils may be required. This will hold the post firmly in the ground, preventing rotation due to wind loads, and help ensure proper operation during impact.

• The embedment depth is important for proper sign assembly operation. One-piece sign assemblies will pull out of the ground if not buried sufficiently deep. If buried too deep, it is difficult to remove the buried segment. Similarly, proper embedment depth for assemblies that use an anchor piece is important to prevent damage to the anchor piece on impact and to prevent rotation due to wind loads. The proper embedment depth varies by type of support system.

• Do not use sign-support sizes larger than required to support the sign or larger than approved for single-support types. For example, a slip base assembly should be used rather than a 6-lb/ft (9-kg/m) U-channel post.

• Do not combine supports, such as square tube inside of pipe, or double the supports, such as back-to-back U-channels.

• Do not use diagonal bracing to strengthen a damaged or improperly designed sup­port system.

• Sign-support assemblies are categorized as unidirectional, bidirectional, and multi­directional. Unidirectional supports will function properly only when impacted from one direction, and bidirectional, from two directions. Multidirectional supports will function properly when impacted from any direction.

• The same type of support post can be configured to operate in different ways upon impact. For example, the U-channel post is basically a unidirectional, base-bending support when buried directly in the ground. It can also be spliced to an anchor piece to provide breakaway characteristics or installed with a frangible coupling to pro­vide multidirectional capability.

• Whenever an anchor system design is used, the anchor stub should not extend more than 4 in (100 mm) above the ground. Extensions above the ground more than this can snag the vehicle undercarriage.

• A minimum mounting height of 9 ft (2740 mm) from the ground to the top of the sign panel is recommended for all single-sign-support installations. Mounting the signs at this minimum height will reduce the possibility of windshield penetration by a sign that bends or yields into the vehicle upon impact.

Advanced Pavement Analysis

The behaviour of unbound granular materials in a pavement structure is stress – dependent. For that reason the linear elastic model is not very suitable. A non-linear elastic model, with an elastic modulus varying with the stress and strain level is, therefore, needed.

For isotropic materials, moduli depend only on two stress invariants1: the mean stress level, p, and the deviatoric stress, q, which are given in the general, as well as the axi-symmetric case (cylindrical state of stress with o1 = oaxial and o2 = o3 =

oradial as:

General

P = T

q = 2 0ij0ij with 0ij = 0ij pSij

In a similar way strain invariants can be introduced. The volumetric strain ev and the deviatoric strain eq, are defined as:

An invariant has the same value regardless of the orientation at which it is measured.

(9.3)

The stresses and strains are interconnected through the material properties as stated in Eq. 9.1 and the elastic (resilient) response of the material can be expressed according to Hooke’s law as a diagonal matrix:

Sv

1

3 (1 – 2v) 0 2

p

Sq_

= E

_ 0 – (1 + v)_

q

where E and v are the material stiffness modulus (or the resilient modulus, usually denoted Mr) and Poisson’s ratio respectively, defined as:

Дq Дє3

Mr or E = and v = – (9.5)

Дє1 Дє1

. * Д p

and Дє„ =

Kr

where Д stands for the incremental change during the loading. An alternative for­mulation is:

where Kr and Gr are the bulk and shear moduli of the material. The bulk and the shear moduli are connected to the resilient modulus and the Poisson’s ratio through:

for isotropic materials.

The resilient modulus for most unbound pavement materials and soils is stress – dependent but the Poisson’s ratio is not, or at least to a much smaller extent. Biarez (1961) described the stress-dependent stress-strain behaviour of granular materials subjected to repeated loading. Independently, similar work was performed in the United States (Hicks and Monismith, 1971). Both results presented the к-0 model, which is written with dimensionless coefficients like:

3 p k2

Mr = ki pa and v = constant (9.8)

PaJ

where Mr is the resilient modulus, p is the mean stress, pa is the reference pres­sure (pa = 100 kPa) and k1, k2 are coefficients from a regression analyses usually based on repeated load triaxial test results. This model has been very popular for
describing non-linear resilient response of unbound granular materials. It assumes a constant Poisson’s ratio and that the resilient modulus is independent of the devia – toric stress. To address this latter limitation the Uzan-Witczak model – often called the “Universal” model – has become widely promoted, especially, in recent years, by authors in North America, e. g. Pan et al. (2006). It takes the form:

Mr = kpa 1 + and v = constant (9.9)

Pa PaJ

Subgrade soils are also stress-dependent and can also be modelled by one of the k-0 approaches. The principle difference between granular materials and many soils is that the former exhibit a strain-hardening stiffness whereas the latter, typically, exhibit strain-softening behaviour under transient stress loadings. In practice, the incorporation of non-linearity into the stiffness computations for subgrade soils is often less important than for granular materials as the stress pulses due to traffic loading will be a far smaller part of the full stress experienced by the subgrade than is the case for the unbound granular layer. Thus the error introduced by ignoring subgrade non-linearity will be correspondingly smaller.

In 1980, Boyce presented some basis for subsequent work on the stress-dependent modelling of the resilient response of cyclically loaded unbound granular material. The Boyce model takes into account both the mean stress and the deviatoric stress, with the bulk and shear moduli, K and G, of the material calculated as:

where Ka, Ga, and n are material parameters determined from curve fitting of re­peated load triaxial tests results.

and q * = уо-j — ст3

Anisotropy of pavement materials is increasingly being recognised as a property that must be modelled if the pavement is to be adequately described (e. g. Seyhan et al., 2005). The Boyce model was modified to include anisotropy in the early 1990’s (Elhannani, 1991; Hornychetal., 1998). Hornych and co-workers ntroduced anisotropy by multiplying the principal vertical stress, cti in the expression of the elastic potential by a coefficient of anisotropy у so that p and q are redefined as follows (c. f. axi-symmetric part of Eq. 9.2):

and the stress-strain relationships are defined as:

Дєq* = 2 (ДЄ1* – Де/) = — and

q 3 1 1 ! 3Gr

Д n*

Дє„ * = Дє1*+ 2Де3* = – .

Kr

Kr and Gr, the bulk and shear moduli, respectively as:

The k— model, Universal model, Boyce model, and the modified Boyce model must be considered in pavement modelling to ensure a valid stress, strain, and deflection evaluation in pavements. When subjected to repeated loading, two types of defor­mations are exhibited, linear or non-linear elastic (or resilient) and plastic deforma­tions. Models based on non-linear elasticity deal with resilient deformations only. Their biggest disadvantage is that permanent deformations cannot be modelled.